How Long Does a London Extension Take to Build?

Typical London extension construction programmes: single-storey rear 12–18 weeks, side return 14–20 weeks, double-storey side extension 18–26 weeks, loft conversion 10–15 weeks and whole-house renovation 22–36 weeks. Programme runs: weeks 1–2 strip-out + foundations; weeks 3–6 superstructure; weeks 7–10 roof + first fix; weeks 11–14 plaster + second fix; weeks 15+ kitchen, finishes, snagging. Heritage and listed work adds 25–50%.

01

Single-storey rear (PD): 12–18 weeks

Weeks 1–2: strip out, set-up, foundations excavated, drainage diversions. Weeks 3–4: foundations poured, oversite, brick to DPC, structural steel set. Weeks 5–7: brick + block superstructure, roof timbers, flat roof or pitched. Weeks 8–10: roof finish (warm flat roof + lantern or pitched + tile), windows and bifolds installed, first-fix M&E, screed. Weeks 11–13: plaster, second-fix M&E, kitchen install. Weeks 14–17: finishes, decoration, flooring, snagging.

02

Loft conversion: 10–15 weeks

Weeks 1–2: scaffolding up, roof opened, structural steel installed (3–5 steels typical). Weeks 3–5: dormer or hip-to-gable built, roof closed and watertight, windows in. Weeks 6–8: floor structure, first-fix M&E, stair installed, insulation. Weeks 9–11: plaster, second-fix, bathroom installed. Weeks 12–14: finishes, decoration, building control completion.

03

Whole-house renovation: 22–36 weeks

Strip-out 2–3 weeks. Structural alterations + extension (if included) 8–12 weeks (parallel programme). Rewire + replumb 3–4 weeks. Plaster 2–3 weeks (dry 2 weeks before paint). Kitchen + bathrooms 3–4 weeks. Finishes + decoration 4–6 weeks. Snagging 1–2 weeks. Parallel workstreams matter — good main contractor sequences trades so plumber finishes pipework just before plaster, electrician returns for second fix just after plaster.

More questions

Related questions answered.

Why do some quotes show shorter programmes?

+

Tight programmes pressure subcontractors and quality. Realistic London 2026 programmes for typical scopes are 12–18 weeks for single-storey, 14–20 weeks for side return.

What causes programme slip?

+

Top three: weather (winter ground-work delays), client variations (extra scope, undecided material specs), discovery (rotten joists, unexpected foundations).

Can I live in during the build?

+

Yes for extensions (kitchen disrupted but liveable) and loft (top floor only). Whole-house renovation — recommend renting out for 8–16 weeks during heaviest disruption.

What is Builderr's typical programme?

+

Single-storey 12–16 weeks, side return 14–18 weeks, loft 10–13 weeks, whole-house 22–32 weeks. We commit to programme dates with weekly progress reports against milestone schedule.