London house extension cost calculator 2026.

Indicative cost ranges for every extension type in London — rear, side return, wrap-around and double-storey. Based on 200+ completed builds. Get a personalised range with your postcode and project size below.

Cost table

2026 London extension costs by type.

TypeCost rangeTimeline
Single-storey rear (3m)£45,000£75,00010–14 wks
Side return£55,000£95,00012–16 wks
Wrap-around (L-shaped)£85,000£145,00016–22 wks
Double-storey rear£95,000£180,00018–24 wks
Kitchen extension (full)£70,000£140,00014–20 wks

Per square metre rates: £2,500–£2,900 standard finish; £3,000–£3,400 high-spec; £3,500–£3,800+ architect-led with bespoke joinery and stone. Glazing-heavy designs (sliding doors, rooflights) trend higher.

Personalised estimate

Build estimator

Get a 60-second estimate

Indicative range
£45,000£120,000
814 weeks on site

FAQ

Extension costs explained.

What is the average cost of a house extension in London 2026?+

Most London extensions cost £2,500–£3,800 per square metre fully fitted, before kitchens and bathrooms. A typical single-storey rear extension runs £45,000–£75,000, side return £55,000–£95,000, wrap-around £85,000–£145,000, double-storey £95,000–£180,000.

What does the extension cost include?+

Foundations, walls, roof, glazing, insulation, electrics, plumbing, heating extension, plaster, flooring, decoration, plus design, structural calculations, planning or LDC fees and party wall agreements. Kitchens and bathrooms quoted separately as PC sums.

Do extensions need planning permission?+

Many rear extensions are permitted development under Class A. Single-storey up to 3m on terraced/semi and 4m on detached. Prior approval extends those to 6m/8m. Double-storey, conservation areas and Article 4 zones always need planning.

How long does an extension take to build?+

Single-storey 10–14 weeks, side return 12–16, wrap-around 16–22, double-storey 18–24. Add 8–10 weeks for planning if needed, 3–4 weeks for design and tender prep.