What's involved
Pre-build CCTV drainage survey to map existing pipework. Engineer's drainage design showing new manholes, gullies, vent stacks and slopes. Connection to existing combined sewer at the boundary. Thames Water build-over agreement if extension footprint crosses or is within 3m of a public sewer.
Thames Water build-over
Mandatory when building over or within 3m of a Thames Water public sewer (most London terraces). Application £350–£700. Pre-works CCTV £600–£1,200. May require sewer reinforcement (lining or replacement) £1,500–£4,000. 6–8 week processing time — apply at planning stage to avoid programme delay.
Hidden costs
Section 106 sewer requisition (if no existing connection): £4,000–£15,000+. Pumped drainage where gravity fall is insufficient (basements, low-lying rears): £2,500–£5,500 for pumping station. Sustainable drainage (SuDS) requirements in some boroughs add soakaways or attenuation: £1,500–£4,500.