Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote

Quick Answer

How Long Does a Bathroom Renovation Take in London?

A typical London bathroom renovation takes 12-18 working days on site for like-for-like replacement, 18-28 days for layout change including new waste runs, and 28-40 days for full reconfigurations involving structural work or master ensuite enlargement. Plan total project duration of 8-14 weeks from design to handover, including supplier lead times.

01

Phase-by-phase bathroom timeline

A standard London bathroom renovation follows six phases. Phase 1 (1-2 days): strip-out of WC, basin, bath, shower, tiles, flooring and any joinery. Phase 2 (2-4 days): first fix plumbing including soil pipe and waste reconfiguration, hot and cold water re-route, shower valve install, underfloor heating mat and wet system pipework. Phase 3 (2-3 days): first fix electrics including ring main isolation, extractor cabling, shaver socket, downlighter wiring, electric underfloor heating mat where chosen. Phase 4 (1-2 days): tanking and waterproofing of wet areas (floors, shower walls to 2m, full wet rooms tanked to 1.8m). Phase 5 (5-10 days): tiling — the longest phase, slowest on large-format or mosaic tiles or with patterned layout. Phase 6 (3-5 days): second fix plumbing and electrics, sanitaryware install, brassware install, vanity and joinery install, accessories, decoration, snag and clean. Total on-site duration 12-28 working days for typical jobs.

02

Supplier lead times to plan around

Sanitaryware lead times in 2026 London: in-stock Roca, Ideal Standard, Twyford 1-2 weeks; imported Italian or Spanish designer fixtures (Catalano, Antoniolupi, Falper) 4-10 weeks; bespoke stone basins or vanities 8-14 weeks. Brassware lead times: in-stock Hansgrohe, Crosswater 1-2 weeks; Drummonds, Lefroy Brooks, Burlington traditional brassware 4-8 weeks; Vola, Dornbracht, Axor designer brass 6-12 weeks. Tile lead times: stocked porcelain and ceramic 1 week; mid-market porcelain 2-4 weeks; natural marble and stone 3-6 weeks (subject to slab inspection); large-format porcelain over 1m 4-6 weeks. Always order everything before site start — site teams cannot work around backorders, and the on-site pause cost of waiting for a delayed item is £400-£800 per day in lost labour productivity.

03

Master ensuite vs family bathroom timeline

Master ensuite renovations typically take 18-28 working days because of higher-spec finishes, bespoke joinery and steam shower or walk-in shower complexity. Family bathrooms typically take 12-18 working days because of simpler layouts (bath plus over-bath shower remains the standard for resale-friendly family homes) and stocked finishes. Cloakrooms and downstairs WCs take 8-14 days. Wet rooms add 3-5 days for the gradient floor screed, drainage and tanking. Master ensuite combined with bedroom reconfiguration (knocking through walls, expanding floor area) becomes a small construction project with 4-7 week total site duration.

More questions

Related questions answered.

Can I keep using my bathroom during renovation?

+

No. Bathroom renovations require complete strip-out and waterproofing of the entire room — water, waste, electrical and structural finishes all come out together. The room is non-functional from day 1 to handover, typically 12-28 working days. If you have only one bathroom, plan for a 3-6 week period without functional bathing facilities. Strategies: install a temporary toilet (£60-£120/month rental of a chemical or composting WC, or convert a utility room to a temporary cloakroom for £400-£800); shower at a gym, swimming pool or family member's home; install a temporary basin and tap in the utility room or kitchen sink area.

What causes bathroom renovation delays?

+

Five issues account for most delays. First, supplier backorders — order everything before site start, store at contractor's premises. Second, hidden damage discovered at strip-out (water-damaged joists, rotting subfloors, asbestos textured ceilings) — budget 1-3 days investigation and remediation. Third, mid-project specification changes (deciding to add underfloor heating after first fix is complete, swapping a bath for a walk-in shower after tile is ordered) — always finalise design before site start. Fourth, tiling complexity — large-format and patterned layouts take 30-50% longer than standard layouts; budget realistically. Fifth, snagging — allow 3-5 days at the end for genuine snags, not 1 day under pressure to complete.

How much does a bathroom renovation disrupt the rest of the house?

+

Less than a kitchen but more than a single bedroom. Expect dust sheeting from the bathroom door to the front door for full duration. Noise levels: high during phase 1 and phase 5 (drill, breaker, tile cutter); moderate during phase 2-4; low during phase 6. Working hours typically 8am-5pm Monday-Friday, sometimes Saturday morning for catch-up. Water and electricity isolations of 2-4 hours on phase 2 and 6 days respectively. WC access affected: arrange a temporary toilet from day 1. Most clients work from home throughout without significant disruption.

Ready to get started?

Senior consultant call within one business hour. Free desk-based planning assessment. Fixed-scope quote — no provisional sums, no day-rate creep.