Extension timeline by type
Timeline varies by extension type and complexity. A side return extension (3–4m wide, single-storey) typically takes 10–14 weeks on site — it's the quickest type because it infills an existing narrow alley, with less new structure than a full rear projection. A single-storey rear extension (4m deep) takes 12–16 weeks. A 6m rear: 14–18 weeks. A wraparound (combining side and rear) adds complexity at the corner junction and typically runs 16–20 weeks. A double-storey rear or side extension is the most complex: foundations must carry two floors, first-floor structure needs careful co-ordination with existing floors, and the roof junction requires skilled detailing — 16–22 weeks on site.
Pre-construction phase breakdown
Before ground breaks, the pre-construction phase takes 6–20 weeks depending on the planning route. Measured survey and design: 2–4 weeks. Structural calculations: 1–2 weeks (usually concurrent with design). Building regulations submission: 2–3 weeks to process. Party wall notice: served at design confirmation, 2-month minimum before structural work, agreement 2–6 weeks for neighbours in agreement or up to 8 weeks for disputed. Permitted development route (LDC): 6–8 weeks application time. Full planning: 8–12 weeks statutory, add 2–4 weeks for preparation. In practice, a PD extension with clear neighbour co-operation: total pre-construction 8–12 weeks. Full planning extension: 14–20 weeks pre-construction.
Month-by-month breakdown for a 4m rear extension
Month 1 (Weeks 1–4): Groundworks — demolition of existing rear wall, foundation excavation, concrete pour, drainage diversion. This is the disruptive month: noise, dust, ground disturbance. Scaffold up around week 3. Month 2 (Weeks 5–8): Superstructure — blockwork walls, structural steel installation over the opening in the existing rear wall, new flat roof deck laid. Extension is weather-tight by end of week 8. This is when the client experience improves significantly. Month 3 (Weeks 9–12): First fix MEP — new wiring, plumbing, UFH if specified, drainage. Insulation, plasterboard. Month 4 (Weeks 13–16): Second fix — final electrics, plumbing connections, tiling, flooring, bifold installation, decoration, kitchen fit-out. Week 16: pre-handover snagging and client walk. Handover.
