Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote

Quick Answer

What Are Liquidated Damages in a London Construction Contract?

Liquidated damages (LDs) are pre-agreed daily compensation if a contractor exceeds the contract completion date. In London residential, typical rates are £100–£500/day depending on project size; agreed at signing under JCT or FMB contract clauses. LDs must reflect a genuine pre-estimate of client's loss (accommodation, finance carrying costs) — not a penalty.

01

Purpose and legal basis

LDs compensate the client for delay beyond completion date — without proof of actual loss. Client shows: completion date passed without extension granted; contractor responsible. LDs apply at agreed daily rate. Legal basis: contractual provision (JCT clause 2.32, FMB Domestic Building Contract clause 19). Must be 'genuine pre-estimate of loss' under English law — penalty clauses void. London residential rates £100–£500/day reflect: temporary accommodation £100–£250/day, additional bridging interest £50–£150/day, storage £20–£50/day, services (cleaning, hotel meals).

02

Typical rates by size

Small extension £75–150k: LDs £100–£250/day; max 10% of contract aggregate. Medium £150–350k: £200–£350/day; max 10–15%. Large renovation £350–800k: £300–£500/day; max 10%. Listed building £500k–£2M+: £400–£800/day. Cap prevents punitive accumulation; reflects practical loss exposure.

03

Extensions of time

Contractor can claim EOT for: client variations, unforeseen ground conditions, force majeure (extreme weather, strikes), client-caused delays (late approvals, access), statutory authority delays (Thames Water, council). Contract administrator assesses; if granted, completion date extended; no LDs to extended period. Disputed EOT: adjudication. Contractor cannot claim EOT for: own resource issues, poor weather (only extreme adverse counts), normal commercial risks.

04

Enforcement

Client enforces by deducting from interim payment certificates: contractor's invoice £25k - LDs accrued £4.5k (15 days × £300) = paid £20.5k. Client must issue formal notice of intent to deduct (JCT clause 2.32.1) before deducting. Adjudication: contractor disputing goes to adjudication; rapid 28-day decision. Court: rare residential. Practical reality: LDs as motivator more than recovery — contractors work to avoid; clients often settle pragmatically.

More questions

Related questions answered.

What's a reasonable LD rate?

+

London residential rule: 0.1–0.3% of contract sum per day, capped 10% aggregate. £200k extension: £200–£600/day, £20k cap. Justify by: accommodation cost in your area (zone 1 hotel £150–£250/day; zone 2 short-term apt £100–£180/day) + finance carrying + storage. Disclose calculation to contractor pre-signing.

Can contractor claim LDs from me for late approvals?

+

Not directly — but contractor can claim Loss and Expense for client-caused delays. JCT clause 4.20. Client late approvals trigger EOT (no LDs to client) + L&E claim (contractor reimbursed direct costs + overhead/profit). Avoid late approvals.

Are LDs enforceable in domestic contracts?

+

Yes — JCT Minor Works or JCT Domestic clauses routinely enforced via adjudication. Enforceable up to genuine pre-estimate of loss. Penalty clauses (sums vastly exceeding likely loss) struck down; cap LDs at realistic level.

What if there's no LD clause?

+

Without LD clause, client must prove actual loss to recover delay damages — burdensome and expensive. Insist on LD clause in any contract over £50k. JCT and FMB standard contracts include LD clauses; FMB Domestic Building Contract most accessible for residential UK.

Ready to get started?

Senior consultant call within one business hour. Free desk-based planning assessment. Fixed-scope quote — no provisional sums, no day-rate creep.