Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote

Quick Answer

What's the Difference Between Consent and Dissent on a Party Wall Notice?

After a London party wall notice is served, the adjoining owner has 14 days to respond. Consent (written agreement) means works proceed with no statutory surveyor process — saves £2,400–£9,000 in surveyor fees + 4–10 weeks programme. Dissent (or no response = deemed dissent under s5) triggers s10 surveyor appointment + Party Wall Award before works can lawfully start. Consent does not waive future damage rights — Schedule of Condition still recommended.

01

Consent — what it means + what it doesn't

Consent must be in writing (s5 Act) — typically a signed + dated counter-signature on the original notice or a separate letter. Consequences of consent: (1) no statutory surveyor appointment required — saves both sides £1,200–£4,500 + VAT in surveyor fees; (2) works may lawfully start once the notice period has expired (1 or 2 months from service depending on section); (3) building owner not exposed to delay from dispute resolution process. What consent does NOT do: it does not waive the adjoining owner's right to claim compensation for damage caused by the works (common-law nuisance + s7 Act statutory liability remain); does not authorise access onto adjoining land (s8 right of access still requires 14-day notice); does not approve specific design or methodology (consent is to proceed, not approval of structural calcs). Best practice with consent: still commission a pre-works Schedule of Condition (£385–£950 + VAT) to record adjoining property baseline — protects building owner from spurious damage claims AND gives adjoining owner evidence base for legitimate claims. Surveyor-prepared SoC valid even where Award process not triggered.

02

Dissent — what triggers it + what happens next

Dissent can be: (1) written dissent within 14 days; (2) silence — adjoining owner who fails to respond within 14 days is 'deemed to have dissented' (s5 Act); (3) any qualified or conditional response that isn't unambiguous consent. Once dissent is triggered, the Party Wall Act's dispute resolution machinery activates (s10): each owner appoints a party wall surveyor (or the parties jointly appoint a single 'agreed surveyor'). The appointed surveyors must produce a Party Wall Award before works lawfully start. Timeline: 4–12 weeks typically (longer for basements + complex schemes). The Award is a statutory document binding both parties — sets out works permitted, methodology, working hours, indemnity, access rights, Schedule of Condition + appointed third surveyor as tie-breaker. Costs of the surveyor process are generally paid by the building owner (s10(13) Act) — typical 2-surveyor process £2,400–£6,500 + VAT, agreed-surveyor route £1,200–£3,500 + VAT, basement schemes £8,000–£25,000 + VAT all paid by building owner. See [[party-wall-award-explained-london]] for content of an Award.

03

Encouraging consent — practical strategy

Building owners can't compel consent but can make it easier: (1) early informal conversation 6–8 weeks before notice — explain scope, drawings, programme, working hours, contact details; build trust; (2) serve clean, complete notice with full drawings + structural calcs + method statement attached (vague notices invite dissent); (3) offer voluntary Schedule of Condition pre-served (paid by building owner) — addresses commonest neighbour fear of damage without evidence; (4) offer voluntary insurance disclosure (contractor's PL £5M + Contract Works); (5) confirm restricted working hours + dust/noise mitigation in writing; (6) where neighbour has a planned extension of their own, offer reciprocal cooperation. Statistics from FPWS member surveys: notices with full drawings + pre-engagement achieve ~55–65% consent rate; notices served cold to neighbours with no prior communication achieve <30% consent. Cost of pre-engagement (6–10 hours of polite conversation + a letter) trivial vs £3,000–£10,000 surveyor process + 6–10 week delay. Where neighbour is hostile or you have prior dispute: don't waste effort, accept dissent route + commission strong party wall surveyor early.

More questions

Related questions answered.

If neighbour consents can they later change their mind?

+

Generally no — once written consent is given for the works as notified, it cannot be unilaterally withdrawn. However: (1) if works deviate from notice (deeper excavation, different structural solution) the consent doesn't cover the variation — fresh notice + 14 days response required; (2) if damage occurs the adjoining owner retains right to compensation regardless of original consent. Document any post-consent variations carefully — variations are the most common source of disputes that ended in consent.

Can I just proceed if neighbour doesn't reply?

+

No — silence is deemed dissent under s5 Act, not deemed consent. After 14 days of no response you MUST appoint a party wall surveyor on the adjoining owner's behalf (s10(4)(b) Act) and proceed via the Award route. Building owner who starts works in the face of deemed dissent without an Award is trespassing + exposed to injunction + damages. Many DIY-builders mistakenly treat silence as approval — costly error.

Does consent save the surveyor fees for both sides?

+

Yes — consent removes the statutory requirement for surveyor appointment entirely. Both sides save the surveyor fees (typically £1,200–£4,500 + VAT each). Adjoining owner can still voluntarily commission a surveyor to review the works + prepare a Schedule of Condition at their own cost (~£500–£950) but building owner has no liability for these fees in a consenting scenario. Significant motivation to encourage consent where neighbours are reasonable.

Ready to get started?

Senior consultant call within one business hour. Free desk-based planning assessment. Fixed-scope quote — no provisional sums, no day-rate creep.