Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote

Construction

FixedPriceversusDayRateContracts:WhyPricingStructureMatters

How a contractor prices your job determines how much risk you carry. Fixed-price, fixed-scope is the default for any project over £20,000. This explains why and how it works.

01

The three pricing models

Construction projects can be priced three ways. Fixed price, fixed scope: contractor quotes a specific sum for a specific scope, with variations only by signed instruction. Day rate (or time-and-materials): contractor charges actual labour days, plus actual materials, plus a markup percentage. Cost-plus: contractor charges actual cost plus a fixed percentage management fee. Each shifts risk differently between client and contractor. For projects under £5,000 (small repairs, callouts), day rate is fine. For projects £5,000–£20,000 (small renovations, single rooms), either model can work. For projects over £20,000 (any meaningful extension or renovation), fixed price is the only sensible model — it puts the risk of over-runs on the contractor, where it belongs.

02

Why fixed price is the default for serious projects

Construction contains many unknowns: ground conditions, existing structure quality, hidden services, weather, supplier delays, planning variations, building control demands. On a fixed-price contract, all of these are the contractor's risk. The client pays the agreed price, period — variations only where the client has changed scope through signed instruction. On a day-rate contract, all of these become the client's risk. Each unforeseen day extends the bill. A 16-week extension that drifts to 22 weeks costs the client 6 weeks of day-rate labour — typically £25,000–£45,000 in overrun. Industry data suggests day-rate contracts run 18–35% over original estimate; fixed-price contracts run 2–5% over (variations only).

03

How we estimate for fixed-price quoting

Producing a robust fixed-price quote requires more upfront work than day-rate scoping. Our process: site survey by senior project manager (2 hours); existing condition assessment including ground investigation if needed (£600–£1,500); structural feasibility consultation; cost build-up against priced bill of quantities; contingency analysis based on project type and known risks; quote draft and internal review; client presentation with line-item visibility. Total quote preparation time: typically 8–14 hours per project, billable as £150–£300 design fee that we credit against the contract sum if you proceed. Why this matters: a robust quote based on thorough investigation is what allows fixed-price to work — vague scoping with optimistic numbers is how cowboys produce 'fixed prices' that grow.

04

Variation orders: how scope changes are managed

Every project has some scope change. The client decides they want a different worktop after seeing the kitchen units installed. Building control requires an additional structural element. The architect spots a detail that would benefit from upgrading. These are handled through written variation orders: contractor issues a variation note with the proposed change, cost impact (additional or saved) and programme impact; client signs to accept or rejects; signed variations become part of the contract. Verbal variations don't exist — we don't act on them, we don't bill for them. This protects both parties: client knows exactly what they're paying for, contractor knows scope is documented. Typical variations on a £100,000 project: 3–8 variations totalling £2,000–£8,000. Never a surprise at final invoice.

05

Provisional sums: a warning sign

Some contractors include 'provisional sums' (PCs) in their quotes — placeholders for line items not yet specified (e.g., 'Kitchen: PC £15,000'). PCs are sometimes legitimate (genuinely undefined scope at quote stage) but more often a vehicle for cost growth: the actual kitchen turns out to cost £22,000, and you pay the difference plus markup. A robust quote either fully specifies each element (£15,000 IKEA, £25,000 Howdens, £45,000 bespoke — pick one before signing) or excludes the element entirely from the contract sum (you buy and supply, we install for a fixed install fee). On our quotes, the only PCs that ever appear are for genuinely impossible-to-price-upfront items like ground investigation surcharges below 1.5m depth — we cap and detail them transparently.

06

Payment schedule on a fixed-price contract

Industry-standard milestone schedule: 5% on contract signature; 15% on site mobilisation; 20% on completion of structural shell (foundations, walls, roof structure); 20% on weather-tight (roof covering, glazing); 20% on first fix complete (services, insulation, plaster); 15% on second fix complete (joinery, decoration, fittings); 5% on Final Certificate. Total = 100%. Each milestone is signed off by the client before invoice is issued. No payment in advance of work being done. A 5% retention is sometimes held against the 6-month defects walk-through. This schedule protects both parties: contractor gets paid as work is delivered, client doesn't pay for work not yet done. Where a contractor wants 40%+ upfront 'to cover materials', be wary — that's a cashflow problem on their end.

FAQ

Common questions.

What if I want to change the scope mid-project?+

Easy — sign a variation order. We'll specify the cost and programme impact in writing, you sign to accept, the change is incorporated. No drama, no surprises.

Do you have hidden costs?+

No. Our quotes are fully itemised, fixed-scope, with all foreseeable costs included. The only mid-project additions are signed variations.

What happens if the project takes longer than quoted?+

Under a fixed-price contract, that's our problem, not yours. We absorb additional management cost. If delay is caused by client variation or genuinely unforeseen condition (ground, planning) we'll discuss and document any agreed adjustment.

Have a project we can help with?

Senior consultant call within one business hour. Free desk-based feasibility check.