Brent · NW6 · 2026

Queen's Park Victorian Side Return + Whole House

Victorian terrace, side return kitchen, dormer loft, full M&E rewire

Project cost
£295,000
Site programme
28 wks
Type
Renovation
Year
2026

Brief

A young family bought a probate Victorian terrace in Queen's Park conservation area needing complete refurbishment — original 1898 plaster intact but layout, services and finishes 1970s. The brief: side return kitchen, L-shape dormer loft for two bedrooms, restored sash windows, full M&E rewire and EPC uplift from E to C.

Challenge

Queen's Park CA required full planning (no PD). Original lath-and-plaster walls and pine floorboards to be preserved where possible — pushed up labour intensity by ~25% vs strip-and-rebuild. Mansard preferred over dormer by conservation officer — final negotiation landed an L-shape dormer with traditional sash window detailing and slate-tile cheek. Discovered chimney breast removal earlier-owner had done was non-compliant — needed retrospective structural sign-off and new gallows brackets at first-floor level. Period sash windows (12 across the house) all needed restoration not replacement under CA rules.

Solution

Side return ground floor 3.8m × 2.2m kitchen-diner with 4.5m bifolds and 1.2 × 2.4m roof lantern; structural opening 4.8m with twin steels. L-shape dormer loft conversion: two bedrooms + bathroom + storage, conservation-compliant slate cheek and timber sash window. Full M&E rewire, replumb, new combi boiler. All 12 sash windows lifted, restored, draught-stripped, secondary-glazed where energy demanded. Lath-and-plaster retained throughout ground floor except where structural breakouts unavoidable. Original pine flooring sanded, refinished oil-only.

Outcome

Footprint added: 8.4m² side return + 26m² loft = 34m² total (+24% on 142m² original). EPC E→C. Heritage features preserved across 95% of original plaster and 100% of original floorboards retained. Conservation officer praised the dormer detailing on completion visit. Programme 28 weeks site + 16 weeks pre-construction. Family moved in week after handover.

Spec

Project specification.

Footprint added
8.4m² side return + 26m² L-shape dormer loft
Structure
4.8m twin 203×203 UB to rear; chimney breast gallows brackets first floor
Sash windows
12 sashes restored, draught-stripped, secondary-glazed (no replacement under CA)
Roof
L-shape dormer with slate-tile cheek, timber sash window (CA-compliant)
M&E
Full rewire, replumb, new combi boiler, EPC E→C
Planning route
Full planning + CA consultation, 12 weeks, 1 amendment
Programme
28 weeks site, 44 weeks total including pre-construction

Gallery

Inside the build.

Side return kitchen with bifolds
Side return kitchen-diner with 4.5m bifolds
L-shape dormer loft bedroom
L-shape dormer master bedroom with conservation-compliant slate cheek
Restored Victorian sash windows
All 12 original sash windows restored and draught-stripped

"Builderr understood Queen's Park from the first site visit — heritage where it mattered, modern where it didn't. The conservation officer was a tough sit-down but they prepared the application properly and we got through with one amendment. The restored sash windows look better than the modern double-glazed units our neighbour put in last year."

Joanna and Marcus Devlin, Queen's Park NW6

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£295,000
a renovation · no provisional sums
Typical builder + variations
£354,000
+£59,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£427,750
+£132,750 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £59,000£132,750 on a renovation.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £295,000.

Want a build like Brent?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services