Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Camden · NW3 · 2026

Grade II listed Hampstead master suite — Calacatta marble + LBC heritage retrofit

Camden · NW3 Hampstead · Grade II Georgian townhouse · 14-week build

Project cost
£165,000
Site programme
14 wks
Type
Bathroom Renovation (master suite — ensuite + dressing room + LBC)
Year
2026

Brief

1820s Grade II listed end-of-terrace Georgian townhouse in Hampstead Village, NW3, within the Hampstead Conservation Area. Owner-occupier family of three. Existing master floor consisted of three small adjoining rooms — a 1950s-rebuild bathroom 4.5m², a small bedroom 9m² and a dressing area 4m² — none with heritage integrity. Brief: combine all three into a single master suite comprising a 14m² master ensuite + 8m² adjoining dressing room, retaining and restoring all original Georgian features including the rear sash window, cornicing, ceiling rose and original pine floorboards. Heritage-luxury specification — book-matched Calacatta Borghini marble, Drummonds + Lefroy Brooks heritage brassware, bespoke fluted walnut joinery.

Challenge

Five issues. (1) Listed Building Consent — works comprised removal of two non-original 1950s internal partitions, but the third partition concealed an original 1820s lath-and-plaster wall with cornice fragments; Camden conservation officer required heritage statement + measured survey + LBC application week 0. (2) Floor structure — combining three rooms onto one floor required removing two non-loadbearing partitions but also exposed undersized original Georgian joists (75×175 over 5m span) that would not take the Calacatta marble floor (45mm slab + adhesive + decoupling ~70kg/m² imposed load on top of the bath); structural engineer specified C24 sister joists 47×220mm in parallel + steel hangers. (3) Marble specification — book-matched Calacatta Borghini at this scale (28m² floor + 42m² walls) needed careful slab selection, vein-matching across 4 quarry runs, and full mock-up approval before fixing. (4) Steam shower — Mr Steam generator vented externally through a discreet brass cowl on a hidden parapet plant zone; conservation officer review required for the external vent. (5) Heating + cooling — listed-building constraints prevent open mechanical AC; underfloor heating + linear concealed cove + a discrete cassette behind reeded-brass grille was the agreed thermal solution.

Solution

Listed Building Consent application Camden Council week 0; pre-application meeting week -3 with Camden Conservation Officer and Hampstead Conservation Area Advisory Committee (CAAC). LBC granted week 18 with 9 conditions covering heritage statement adherence, weekly progress reports to conservation officer during enabling works, retention of original 1820s lath-and-plaster wall fragments, recording of all original features pre-strip, and approval-in-writing of marble specification mock-up. Build phase 14 weeks following LBC + Building Control. Weeks 1–3 enabling works + protection + recording. Original Georgian sash window protected with bespoke ply over-cover. Original pine floor lifted under conservation officer supervision, numbered, palleted for re-laying in a salvage-grade subset within the dressing room. Original 1820s lath-and-plaster wall fragments retained where possible behind new dry-lining. Weeks 4–6 structural — C24 47×220mm sister joists bolted to existing 75×175mm Georgian joists + new steel hangers to pocket details + acoustic insulation Rockwool Flexi 100mm between joists. Soil-pipe relocation internally via boxed chase through party-wall void (with Party Wall Award already issued and consented). Mr Steam generator (MS-150) installed in adjacent plant cupboard + 50mm flexible stainless duct routed to discreet brass cowl on rear parapet (conservation officer approved colour-matched bronze patination). Weeks 7–10 first fix + waterproofing. Schlüter-KERDI membrane over 22mm marine ply overlay bedded in epoxy + KERDI-DRAIN linear drain to walk-in steam shower. Underfloor heating Wunda 16mm low-profile wet UFH zoned across ensuite + dressing room + powered by retained Vaillant ecoFIT 935 system boiler. Weeks 9–12 marble fixing. Calacatta Borghini 20mm slab format 1200×600mm to floor + walls; book-matched bookend pattern across 4 quarry runs (Carrara region); full vein-mock-up approved by client + conservation officer week 7; fixed with Mapei Adesilex P10 white slow-set adhesive + epoxy grout + sealed Hydroshield 3-coat post-fix. Walk-in steam shower 2m × 1.2m with 10mm low-iron glass screen + Calacatta marble bench + Mr Steam controls + Lefroy Brooks Mackintosh aged-brass shower set with overhead rainshower + handheld + body jets. Drummonds Tay 1800mm cast-iron freestanding bath on Lefroy Brooks ball-and-claw aged-brass feet + Lefroy Brooks floor-mounted bath filler. Weeks 11–13 joinery + furniture. Bespoke his-and-hers fluted walnut vanity 2.4m wide + Calacatta Borghini worktop with integrated brass towel rails + reeded brass mirror cabinets above + integrated LED + downlight. Adjoining dressing room 8m² bespoke fluted walnut wardrobes + island chest + brass ironmongery + LED interior lighting on motion sensor + reclaimed original Georgian sash window restored in situ + Selectaglaze secondary glazing for acoustic + thermal. Brass concealed cassette AC behind reeded-brass grille in ceiling, vented externally through same parapet plant zone as steam vent. Heritage retention — cornice fragments retained + replicated where missing by Pavilion Plaster; ceiling rose retained; original pine floor re-laid in dressing room as salvage-grade feature. Week 14 commissioning + LBC discharge + Building Control final + handover.

Outcome

LBC discharged + Building Control final certificate issued week 14. Project completed Q1 2026, on programme. Master suite transformed from three undersized 1950s-modified rooms (17.5m² total) to a coherent 22m² master suite (14m² ensuite + 8m² dressing room) with heritage-luxury spec matching the rest of the recently restored townhouse. Resale agent (Goldschmidt & Howland Hampstead) valued the suite uplift at £285,000 against £165,000 spend = 173% gross ROI. Project featured in House & Garden Bathrooms June 2026 cover story, Drummonds case study Q3 2026, and Lefroy Brooks UK Heritage Bathrooms Awards 2026 finalist. Builderr first Grade II listed master-suite LBC project + first Calacatta Borghini book-matched bookend at 70m² scale + first Mr Steam steam shower in a listed building with conservation officer-approved external vent + first parallel LBC + Building Control + Party Wall Award delivery on a master-suite-only scope. Camden 4th portfolio case study + Hampstead first.

Spec

Project specification.

Property
1820s Grade II listed end-of-terrace Georgian townhouse NW3 Hampstead Village; Hampstead Conservation Area; owner-occupier; recent ground-floor + first-floor heritage restoration completed by other contractors prior
Scope
Combine three small rooms (1950s bathroom 4.5m² + small bedroom 9m² + dressing area 4m²) into 14m² master ensuite + 8m² adjoining dressing room; full LBC heritage retrofit retaining all original Georgian features
Heritage approvals
Listed Building Consent Camden Council granted week 18 with 9 conditions; Hampstead CAAC pre-app review; Heritage Statement + measured survey + photographic record + retained-feature register; conservation officer weekly progress visits during enabling works
Structural
C24 47×220mm sister joists bolted to original 75×175mm Georgian joists + steel hangers to pocket details + Rockwool Flexi 100mm acoustic; floor capacity uprated to take Calacatta Borghini 20mm slab + bath point load
Marble
Calacatta Borghini 20mm slab 1200×600mm to 28m² floor + 42m² walls; book-matched bookend pattern across 4 quarry runs (Carrara region); Mapei Adesilex P10 white slow-set adhesive + epoxy grout + sealed Hydroshield 3-coat; full vein mock-up approved by client + conservation officer week 7
Bath + brassware
Drummonds Tay 1800mm cast-iron freestanding bath on Lefroy Brooks Mackintosh aged-brass ball-and-claw feet; Lefroy Brooks Mackintosh aged-brass floor-mounted bath filler + thermostatic mixer; all secondary brassware Lefroy Brooks Mackintosh
Steam shower
Walk-in steam shower 2m × 1.2m — Mr Steam MS-150 generator in adjacent plant cupboard + 50mm stainless flex duct to discreet bronze-patinated cowl on rear parapet (conservation officer approved); Calacatta marble bench; Lefroy Brooks overhead + handheld + body jets; 10mm low-iron glass screen
Vanity
Bespoke his-and-hers fluted walnut double-basin vanity 2.4m + Calacatta Borghini worktop + integrated brass towel rails + reeded brass mirror cabinets + integrated LED
Dressing room
8m² bespoke fluted walnut wardrobes + island chest + brass ironmongery + LED interior on motion sensor; restored original Georgian sash window + Selectaglaze secondary glazing
Waterproofing
Schlüter-KERDI membrane over 22mm marine ply overlay bedded in epoxy + KERDI-DRAIN linear drain to walk-in steam shower; tanked-to-ceiling wet zone
Heating + cooling
Wunda 16mm low-profile wet UFH zoned ensuite + dressing room (Vaillant ecoFIT 935 system boiler retained); concealed brass cassette AC behind reeded-brass grille (vented externally via same parapet plant zone)
Heritage retention
Original 1820s cornice fragments retained + replicated where missing by Pavilion Plaster; ceiling rose retained; original pine floor re-laid in dressing room as salvage feature; original 1820s lath-and-plaster wall fragments retained behind dry-lining
Party Wall
3-party Party Wall Award (attached neighbours both sides + freeholder); Peter Barry surveyor £4,800; schedule of condition; no disputes
Cost + ROI
All-in £165,000 build (incl marble £42k + Drummonds + Lefroy Brooks £28k + bespoke joinery £24k + structural + LBC heritage works + steam shower + AC + finishes + fees); resale agent uplift £285,000 = 173% gross ROI
Programme
14 weeks build (on programme); LBC pre-build phase week -18 to week 18 parallel; Q1 2026 completion
Awards + recognition
House & Garden Bathrooms June 2026 cover story; Drummonds case study Q3 2026; Lefroy Brooks UK Heritage Bathrooms Awards 2026 finalist

Gallery

Inside the build.

Master ensuite Calacatta marble walls and floor
Master ensuite — book-matched Calacatta Borghini marble walls + floor; Drummonds Tay 1800mm cast-iron freestanding bath; Lefroy Brooks Mackintosh aged-brass
Walk-in steam shower with marble
Walk-in steam shower 2m × 1.2m — Mr Steam generator + low-iron glass screen + Calacatta marble bench + Lefroy Brooks shower set
His-and-hers vanity in fluted walnut
His-and-hers double-basin vanity 2.4m fluted walnut + Calacatta Borghini worktop + integrated brass towel rails + reeded brass mirror cabinets
Dressing room with bespoke joinery
Adjoining dressing room 8m² — bespoke fluted walnut wardrobes + island chest + brass ironmongery + restored original Georgian sash window

"The first contractor we spoke to didn't understand listed building work — they wanted to strip everything back including the lath-and-plaster fragments behind the 1950s partitions. Builderr's heritage instinct was different from the first meeting — they walked the house with our Heritage Statement author from Donald Insall Associates and Camden's conservation officer before quoting. The Calacatta Borghini book-match across four quarry runs took eight weeks of slab selection in Carrara — Builderr's stone consultant flew out twice with us. The Mr Steam external vent through the rear parapet was the moment I knew we'd chosen well — they'd already worked out the conservation officer approval before we even raised it. 14 weeks, on programme, with weekly conservation officer visits and a 9-condition LBC delivered cleanly. House & Garden cover June 2026."

Lady Catherine W., Hampstead Village NW3

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£165,000
a bathroom renovation (master suite — ensuite + dressing room + lbc) · no provisional sums
Typical builder + variations
£198,000
+£33,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£239,250
+£74,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £33,000£74,250 on a bathroom renovation (master suite — ensuite + dressing room + lbc).

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £165,000.

Want a build like Camden?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services