Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Croydon · CR8 · 2026

Purley 1930s Double-Storey Side + Rear Extension

1930s semi, double-storey side, single-storey rear, open-plan reno

Project cost
£185,000
Site programme
22 wks
Type
Extension
Year
2026

Brief

A family of four in a 3-bed Purley 1930s semi needed downstairs entertaining space and an additional bedroom + en-suite upstairs. The brief: double-storey side extension + single-storey rear + open-plan ground floor remodel. No conservation area; PD route attractive.

Challenge

Outer London delivery logistics: tighter labour pool and longer lead times on specialist trades than inner London. Sloping plot — rear garden 1.1m higher than ground floor — required stepped foundations and a half-flight lift between dining area and garden door. Existing party wall to north neighbour needed Party Wall Act notices (single Surveyor route agreed, £1,400). Family wanted to remain in occupation throughout — necessitated phased works with temporary kitchen for 9 weeks.

Solution

Double-storey side extension 3.4m × 7.8m: ground floor extending kitchen, first floor adding 4th bedroom + en-suite. Single-storey rear 4m × 5.6m for living-dining with 5m bifolds and double roof lanterns. Ground floor fully open-plan from front to back. Stepped foundations stepped 600mm at rear due to slope. Half-flight of three steps internal between dining and garden floor — turned into a feature with built-in seating and timber detail. Phased works: side extension first (kitchen + bedroom roughed out); 2-week kitchen relocation to side extension; rear extension built; final fit-out.

Outcome

Internal floor area increased from 94m² to 145m² (+54%). Family remained in occupation throughout — no rental costs. Full PD route saved 8 weeks vs full planning. Phased programme came in 22 weeks. EPC C maintained (1930s cavity walls already insulated). Family Christmas in the new open-plan space before site completion.

Spec

Project specification.

Footprint added
26m² double-storey side + 22m² single-storey rear = 48m² ground / 26m² first
Structure
5m steel beam to rear; double-storey side load-bearing cavity walls
Foundations
Stepped 600mm at rear due to garden slope
Roof lanterns
2 × 1.2 × 2.4m double-glazed aluminium
Planning route
Permitted Development — no application required
Party Wall
Single Surveyor (both neighbours agreed), £1,400 fee
Programme
22 weeks site, phased to allow occupation throughout

Gallery

Inside the build.

Open-plan ground floor
Ground floor open-plan from front to back
Single-storey rear extension
Rear extension with double roof lanterns and 5m bifolds
New first-floor bedroom
Fourth bedroom + en-suite over the side extension

"We were anxious about staying in occupation during such a big build but Builderr's phased approach worked. The double-storey side gave us the extra bedroom we'd been priced out of getting in a bigger house and the rear extension means the kitchen-living-garden flows the way modern family life actually works. PD route saved us months."

Steve and Priya Walters, Purley CR8

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£185,000
a extension · no provisional sums
Typical builder + variations
£222,000
+£37,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£268,250
+£83,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £37,000£83,250 on a extension.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £185,000.

Want a build like Croydon?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services