Ealing · W5 · 2026

Double-Storey Side Extension, Ealing Edwardian Semi

A 44 sqm double-storey side extension delivering a family kitchen-diner downstairs and master suite upstairs on a 1908 Ealing semi.

Project cost
£178,000
Site programme
20 wks
Type
Double-Storey Side Extension
Year
2026

Brief

A 1908 Ealing semi where a young professional family had outgrown the original cellular ground floor plan and needed both a family kitchen-diner and an additional bedroom suite. The plot had a 3.2m side return — wide enough for a substantial double-storey extension subject to planning approval on a street within the Walpole Conservation Area buffer.

Challenge

Ealing's conservation team flagged early concern that a full-width double-storey side extension would erode the rhythm of original Edwardian semis on the street. The standard 1m first-floor setback was required but the brickwork match also needed to be exact — Ealing officers specifically inspect mortar colour, brick bond and lintel detailing on extensions within conservation area buffers. The household also had a strict 'no live-in renovation' requirement requiring an aggressive programme.

Solution

We commissioned a brick survey of three adjacent semis to identify the exact London stock match (a soft red Fareham stock with Flemish bond) and submitted material samples with the planning application. The first-floor setback was articulated with a stepped brick course shadow gap reading as a deliberate join rather than a flat continuation. Internally a 6.2m steel goalpost frame opened the ground floor for the new kitchen-diner, with a steel ridge beam reframing the existing roof valley to accommodate the new upstairs bedroom. Programme was compressed to 20 weeks with two-shift fit-out and prefabricated kitchen units.

Outcome

Planning approved at 9 weeks first-time with no objections from the conservation team — the brick survey and stepped joint detailing were specifically commended in the officer's report. Site completed in 20 weeks against a 20-week programme. Both party wall awards agreed amicably. Resale agent valued the uplift at £310,000 against £178,000 spend.

Spec

Project specification.

Floor area added
44 sqm (22 sqm ground + 22 sqm first)
Rooms added
Kitchen-diner + master bedroom + ensuite
Structural steel
2.4 tonnes (goalpost + ridge + lintels)
Brick match
Soft red Fareham stock, Flemish bond, lime mortar
Glazing U-value
1.1 W/m²K (sliding doors), 1.2 W/m²K (sashes)
Programme
20 weeks on site, 10 months total

Gallery

Inside the build.

Open-plan kitchen-diner in side extension
New kitchen-diner runs the full length of the side extension with sliding doors to the garden.
Master bedroom upstairs
Master bedroom over the new ground floor extension with original Edwardian bay retained to the front.
Master ensuite
Walk-in shower ensuite with porcelain stone-effect tiling and underfloor heating.
External brick detail matching original
London stock brick courses matched to the original Edwardian elevation with sash window proportions retained.

"Ealing's conservation team have a reputation for being tough on materials match. Builderr's brick survey turned what could have been a refusal into a commended approval. The finished extension reads as if the house was built this way in 1908 — and the family lived elsewhere through the build with zero hassle."

Anika and Tom Sharma, Ealing W5

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£178,000
a double-storey side extension · no provisional sums
Typical builder + variations
£213,600
+£35,600 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£258,100
+£80,100 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £35,600£80,100 on a double-storey side extension.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £178,000.