Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Ealing · W5 · 2026

1930s semi rear extension + loft + energy retrofit, W5

Ealing · 1934 mock-Tudor semi · W5 · 26-week build

Project cost
£285,000
Site programme
26 wks
Type
Whole House
Year
2026

Brief

A 1934 mock-Tudor semi on Pitshanger Lane W5, mid-tier Ealing residential market. Clients: a software architect and gallery curator with two young children planning a 15-year hold; brief was a comprehensive 'forever home' renovation transforming a tired 3-bed (90m² original) into a 5-bed family home (148m² post-renovation) with deep-retrofit thermal upgrade and open-plan family living. Budget £285k including ASHP, MVHR, full rewire, replumb, kitchen, two bathrooms and external works. Phased works programme — family vacated to rental for 26 weeks. Pitshanger Lane within character area but not formally conservation area; permitted development applied with prior approval for the 6m larger home extension neighbour consultation.

Challenge

Three connected challenges. (1) The 1934 mock-Tudor envelope (cavity wall, brick + tile-hung first floor, half-timbered gables, double-bayed front) had to be retained completely on the front and side elevations — Ealing planning officer pre-application advice was clear that visible elevations must preserve mock-Tudor character even though property is not formally listed or in a conservation area; rear elevation could be modernised. (2) Deep-retrofit thermal upgrade (cavity wall insulation, internal wall insulation to solid party wall, loft 400mm, suspended floor insulation 150mm, MVHR ducting, ASHP integration with retained-and-upsized radiator network) required floors up, ceilings down, and full service replacement — sequencing critical to maintain 26-week programme. (3) Hip-to-gable loft conversion required rebuilding the original mock-Tudor hip-end gable in matching salvaged tile-hanging and authentic half-timbered cladding — sourcing reclaimed materials and matched-profile timber added 3 weeks of lead time but was non-negotiable for visual consistency.

Solution

Pre-construction phase (10 weeks): MCS heat loss survey, ASHP design at 9kW Vaillant aroTHERM plus R290 with weather compensation; emitter audit (8 existing radiators retained, 6 upsized Type 22 → Type 33, 3 new for new loft and extension); MVHR design Zehnder ComfoAir Q350 with PE100 semi-rigid ducting routed in service voids; Pitshanger Lane neighbour consultation for 4.5m single-storey rear (8 weeks Prior Approval) and certificate of lawfulness for hip-to-gable loft (8 weeks). Build programme weeks 1–26. Weeks 1–4: strip-out, floors up, asbestos abatement (Artex ceilings throughout — Type 2 survey identified £2,800 abatement); structural steel for rear opening 6.2m × 3.0m + new loft trimmer; Pitshanger party wall notices to one neighbour (semi-detached). Weeks 5–10: rear extension construction (single-storey, traditional masonry to match existing brick, EPDM flat roof with two integrated rooflights, aluminium bifold doors); foundations on existing strip foundation extended; building control inspections at each stage. Weeks 11–16: hip-to-gable loft construction (steel beams, rebuild gable in salvaged tile-hanging from Tilbury Reclaim, half-timber cladding in seasoned oak with linseed-oil finish matched to existing), rear dormer, new staircase to loft from first-floor landing. Weeks 17–22: M&E first-fix — full rewire (CU+RCD), full replumb, ASHP install + 250L heat-pump-compatible cylinder + MVHR install + UFH wet to ground floor (75mm screed); CWI to cavity walls; internal wall insulation 60mm PIR to two party walls; loft insulation 400mm; suspended floor insulation 150mm. Weeks 23–26: second-fix, kitchen install (Howdens Burford Cashmere with Caesarstone Statuario worktop and 1.8m island), bathrooms × 2 (Villeroy & Boch + Crosswater), decoration, snagging. Ealing planning prior approval granted at week 8; building control completion certificate week 27. EPC E (54) → B (84).

Outcome

Comprehensive 'forever home' delivered on programme and budget (£287,500 final, 0.9% over £285,000 budget on additional asbestos abatement). 5-bedroom family home with master suite in loft, open-plan family kitchen-diner-living on ground floor, original front elevation mock-Tudor character retained intact. EPC improvement E (54) → B (84) — 30-point improvement; annual heating bill £2,800 (gas combi pre-renovation) → £980 (ASHP at SCOP 3.8); £1,820 annual saving; BUS grant £7,500 contributed; net ASHP install £4,200. Floor area 90m² → 148m² (+64%). Property valuation: pre-renovation £880,000; post-renovation £1,265,000 (£385,000 uplift on £287,500 build cost — 134% gross ROI). Pitshanger Lane neighbour consultation completed without objection; planning officer praised retention of mock-Tudor character. Pitshanger first case study for Builderr portfolio.

Spec

Project specification.

Property
1934 mock-Tudor semi, Pitshanger Lane W5, character area, 90m² original
Planning
Prior Approval for 4.5m single-storey rear; certificate of lawfulness for hip-to-gable loft; mock-Tudor front retained
Heating
Vaillant aroTHERM plus R290 9kW ASHP, SCOP 3.8 at 50°C flow; 250L heat-pump cylinder; wet UFH ground floor; upsized radiators upstairs
Ventilation
Zehnder ComfoAir Q350 MVHR, PE100 semi-rigid ducting in service voids, 90% heat recovery efficiency
Fabric
Cavity wall insulation bond-blown; 60mm PIR internal to party walls; 400mm loft insulation; 150mm suspended floor; secondary glazing to retained front bays
Loft
Hip-to-gable + rear dormer; rebuilt gable in salvaged tile-hanging + seasoned-oak half-timber cladding (Tilbury Reclaim source)
Extension
Single-storey rear 4.5m × 6.2m; aluminium bifold 5m wide; two 1.2m × 1.0m rooflights; EPDM flat roof with parapet
EPC
E (54) → B (84) — 30-point uplift
Floor area
90m² → 148m² (+64%); 3-bed → 5-bed
Programme
26 weeks build, 36 weeks total inc. 10 weeks pre-construction
ROI
£287,500 build → £385,000 sale value uplift / 134% gross ROI

Gallery

Inside the build.

1930s semi rear extension and loft Pitshanger Ealing W5
Pitshanger Lane 1934 mock-Tudor semi — single-storey rear (4.5m PD) + hip-to-gable loft + EPC E→B
Open-plan kitchen diner rear extension Ealing
Open-plan kitchen-diner — 5.6m × 6.2m, aluminium bifolds, two 1.2m rooflights, wet UFH on ASHP
Hip-to-gable loft master suite Pitshanger
Hip-to-gable loft — master bedroom + en-suite + dressing area, 28m² added, restored mock-Tudor cladding to gable

"We bought the house knowing it needed everything — and also knowing we couldn't touch the front. Builderr ran the project like a deep-retrofit specialist. The heat pump and MVHR were specified before steel was on order; the gable rebuild used salvaged tiles that look like they've been there since 1934. We came back to a house that's twice the size, half the running cost, and visually still our 1934 Pitshanger Lane semi."

Ravi and Hannah Kashyap, Pitshanger W5

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£285,000
a whole house · no provisional sums
Typical builder + variations
£342,000
+£57,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£413,250
+£128,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £57,000£128,250 on a whole house.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £285,000.

Want a build like Ealing?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services