Skip to content
Projects
AnswersInsights
Get a Quote
020 7864 7245WhatsApp
Ealing · W5 · 2026

1930s semi rear extension + loft + energy retrofit, W5

Ealing · 1934 mock-Tudor semi · W5 · 26-week build

Project cost
£285,000
Site programme
26 wks
Type
Whole House
Year
2026

Free · No obligation

Get your free quote

A senior consultant calls within one business hour.

No spam. Your details are never sold.

Brief

A 1934 mock-Tudor semi on Pitshanger Lane W5, mid-tier Ealing residential market. Clients: a software architect and gallery curator with two young children planning a 15-year hold; brief was a comprehensive 'forever home' renovation transforming a tired 3-bed (90m² original) into a 5-bed family home (148m² post-renovation) with deep-retrofit thermal upgrade and open-plan family living. Budget £285k including ASHP, MVHR, full rewire, replumb, kitchen, two bathrooms and external works. Phased works programme — family vacated to rental for 26 weeks. Pitshanger Lane within character area but not formally conservation area; permitted development applied with prior approval for the 6m larger home extension neighbour consultation.

Challenge

Three connected challenges. (1) The 1934 mock-Tudor envelope (cavity wall, brick + tile-hung first floor, half-timbered gables, double-bayed front) had to be retained completely on the front and side elevations — Ealing planning officer pre-application advice was clear that visible elevations must preserve mock-Tudor character even though property is not formally listed or in a conservation area; rear elevation could be modernised. (2) Deep-retrofit thermal upgrade (cavity wall insulation, internal wall insulation to solid party wall, loft 400mm, suspended floor insulation 150mm, MVHR ducting, ASHP integration with retained-and-upsized radiator network) required floors up, ceilings down, and full service replacement — sequencing critical to maintain 26-week programme. (3) Hip-to-gable loft conversion required rebuilding the original mock-Tudor hip-end gable in matching salvaged tile-hanging and authentic half-timbered cladding — sourcing reclaimed materials and matched-profile timber added 3 weeks of lead time but was non-negotiable for visual consistency.

Solution

Pre-construction phase (10 weeks): MCS heat loss survey, ASHP design at 9kW Vaillant aroTHERM plus R290 with weather compensation; emitter audit (8 existing radiators retained, 6 upsized Type 22 → Type 33, 3 new for new loft and extension); MVHR design Zehnder ComfoAir Q350 with PE100 semi-rigid ducting routed in service voids; Pitshanger Lane neighbour consultation for 4.5m single-storey rear (8 weeks Prior Approval) and certificate of lawfulness for hip-to-gable loft (8 weeks). Build programme weeks 1–26. Weeks 1–4: strip-out, floors up, asbestos abatement (Artex ceilings throughout — Type 2 survey identified £2,800 abatement); structural steel for rear opening 6.2m × 3.0m + new loft trimmer; Pitshanger party wall notices to one neighbour (semi-detached). Weeks 5–10: rear extension construction (single-storey, traditional masonry to match existing brick, EPDM flat roof with two integrated rooflights, aluminium bifold doors); foundations on existing strip foundation extended; building control inspections at each stage. Weeks 11–16: hip-to-gable loft construction (steel beams, rebuild gable in salvaged tile-hanging from Tilbury Reclaim, half-timber cladding in seasoned oak with linseed-oil finish matched to existing), rear dormer, new staircase to loft from first-floor landing. Weeks 17–22: M&E first-fix — full rewire (CU+RCD), full replumb, ASHP install + 250L heat-pump-compatible cylinder + MVHR install + UFH wet to ground floor (75mm screed); CWI to cavity walls; internal wall insulation 60mm PIR to two party walls; loft insulation 400mm; suspended floor insulation 150mm. Weeks 23–26: second-fix, kitchen install (Howdens Burford Cashmere with Caesarstone Statuario worktop and 1.8m island), bathrooms × 2 (Villeroy & Boch + Crosswater), decoration, snagging. Ealing planning prior approval granted at week 8; building control completion certificate week 27. EPC E (54) → B (84).

Outcome

Comprehensive 'forever home' delivered on programme and budget (£287,500 final, 0.9% over £285,000 budget on additional asbestos abatement). 5-bedroom family home with master suite in loft, open-plan family kitchen-diner-living on ground floor, original front elevation mock-Tudor character retained intact. EPC improvement E (54) → B (84) — 30-point improvement; annual heating bill £2,800 (gas combi pre-renovation) → £980 (ASHP at SCOP 3.8); £1,820 annual saving; BUS grant £7,500 contributed; net ASHP install £4,200. Floor area 90m² → 148m² (+64%). Property valuation: pre-renovation £880,000; post-renovation £1,265,000 (£385,000 uplift on £287,500 build cost — 134% gross ROI). Pitshanger Lane neighbour consultation completed without objection; planning officer praised retention of mock-Tudor character. Pitshanger first case study for Builderr portfolio.

Spec

Project specification.

Property
1934 mock-Tudor semi, Pitshanger Lane W5, character area, 90m² original
Planning
Prior Approval for 4.5m single-storey rear; certificate of lawfulness for hip-to-gable loft; mock-Tudor front retained
Heating
Vaillant aroTHERM plus R290 9kW ASHP, SCOP 3.8 at 50°C flow; 250L heat-pump cylinder; wet UFH ground floor; upsized radiators upstairs
Ventilation
Zehnder ComfoAir Q350 MVHR, PE100 semi-rigid ducting in service voids, 90% heat recovery efficiency
Fabric
Cavity wall insulation bond-blown; 60mm PIR internal to party walls; 400mm loft insulation; 150mm suspended floor; secondary glazing to retained front bays
Loft
Hip-to-gable + rear dormer; rebuilt gable in salvaged tile-hanging + seasoned-oak half-timber cladding (Tilbury Reclaim source)
Extension
Single-storey rear 4.5m × 6.2m; aluminium bifold 5m wide; two 1.2m × 1.0m rooflights; EPDM flat roof with parapet
EPC
E (54) → B (84) — 30-point uplift
Floor area
90m² → 148m² (+64%); 3-bed → 5-bed
Programme
26 weeks build, 36 weeks total inc. 10 weeks pre-construction
ROI
£287,500 build → £385,000 sale value uplift / 134% gross ROI

Gallery

Inside the build.

1930s semi rear extension and loft Pitshanger Ealing W5
Pitshanger Lane 1934 mock-Tudor semi — single-storey rear (4.5m PD) + hip-to-gable loft + EPC E→B
Open-plan kitchen diner rear extension Ealing
Open-plan kitchen-diner — 5.6m × 6.2m, aluminium bifolds, two 1.2m rooflights, wet UFH on ASHP
Hip-to-gable loft master suite Pitshanger
Hip-to-gable loft — master bedroom + en-suite + dressing area, 28m² added, restored mock-Tudor cladding to gable

"We bought the house knowing it needed everything — and also knowing we couldn't touch the front. Builderr ran the project like a deep-retrofit specialist. The heat pump and MVHR were specified before steel was on order; the gable rebuild used salvaged tiles that look like they've been there since 1934. We came back to a house that's twice the size, half the running cost, and visually still our 1934 Pitshanger Lane semi."

— Ravi and Hannah Kashyap, Pitshanger W5

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£285,000
a whole house · no provisional sums
Typical builder + variations
£342,000
+£57,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£413,250
+£128,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £57,000–£128,250 on a whole house.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £285,000.

Want a build like Ealing?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services