Georgian whole-house renovation — Maritime WHS buffer
Greenwich · 1798 Grade II Georgian terrace · 32-week programme
Brief
Grade II listed 1798 Georgian terrace on the south side of Blackheath, 380m inside the Maritime Greenwich World Heritage Site 1.5km buffer zone. Owners — second home becoming primary residence — wanted full top-to-bottom heritage restoration reversing 1970s and 1990s sympathetic-but-clumsy interventions, with full M&E renewal, kitchen and bathroom reconfiguration, and sash restoration in situ. Building previously held the Blackheath Society's worst-condition listed-stock case study (2018).
Challenge
Triple-layered consents: Greenwich LBC + full planning for two minor external interventions + Historic England consultation (statutory under WHS buffer + Grade II + group-listed terrace) + Blackheath Society pre-app review. 1970s gypsum plaster and 1990s plasterboard removed had concealed 64m of original lime cornice in salvageable condition + 4 of 5 original marble chimneypieces (one missing entirely — sourced from Lassco). Electrical and plumbing chases through 230mm solid-brick walls required Hayles & Howe-supervised lime patching. ASHP placement banned to all elevations facing the Heath under WHS view-impact policy — relocated to rear courtyard behind a 1.8m timber acoustic screen. All 18 original sash windows refused replacement consent — restoration in situ only, with Selectaglaze secondary glazing as the thermal/acoustic answer.
Solution
26-week design and consents phase: LBC + planning + Historic England consultation submitted week 4, determined week 22 (cleared without amendments after Blackheath Society + Greenwich Conservation Officer + Historic England all letters-of-no-objection). 32-week site programme phased into structural-first (weeks 1–10: lime plaster strip, structural opening to closet wing alcove with 178×102 UB tucked into spine wall, all M&E first fix, sash removal and bench-restoration by Mumford & Wood at their Norwich workshop), heritage-finishes (weeks 11–22: Hayles & Howe 64m original cornice retention + 18m new run-in-situ replication, 4 original marble chimneypieces restored + 1 Westland-sourced 1810 Carrara replacement, lime plaster reinstatement throughout, restored pitch-pine floor sand-and-restore + 4 boards Crown Reclamation match), and finishes (weeks 23–32: Plain English Marylebone kitchen with Calacatta Borghini worktop, Drummonds Spey roll-top + Lefroy Brooks Mackintosh thermostatic + Burlington traditional WCs across all 4 bathrooms, Edward Bulmer paint throughout, reinstated original Holland blinds via Holland & Sherry, Selectaglaze Series 10 secondary glazing on all 18 sashes — Rw 38dB attenuation against Heath-facing traffic and overflight noise).
Outcome
LBC + planning + Historic England cleared week 22 without amendments — Blackheath Society described the application as 'an exemplar of evidence-led restoration' in its consultation letter. Site completed week 32, two days inside programme. Original 64m cornice retained + 18m replicated indistinguishable on close inspection (Hayles & Howe). 18 sashes restored in situ + Selectaglaze secondary glazing achieved U-value 1.4 W/m²K (better than Part L 1.4 target for replacement glazing) without losing original Crown glass. ASHP 32 dB(A) at 1m below WHS-required 35 dB(A). EPC F (28) → C (72) — exceptional for a Grade II Georgian with full sash retention. Resale-equivalent uplift £1.04M against £612k spend = 170% gross ROI. Building listed as Blackheath Society's 2026 Restoration Award winner; Historic England commendation in WHS Annual Report 2026; AJ Retrofit Awards 2026 Listed Building shortlist; Country Life 6-page feature January 2027.
Spec
Project specification.
Gallery
Inside the build.
"We bought a 1798 Georgian listed terrace in the Blackheath WHS buffer that the Blackheath Society had publicly named as their worst-condition listed building of 2018. We needed a contractor who could navigate Greenwich LBC + full planning + Historic England consultation + the Blackheath Society pre-app review as a single coordinated workstream, run a 32-week site programme without losing any of the original lime cornice or the Crown glass, and deliver a heritage restoration that would change the building's standing in the borough. Builderr cleared all four consents at week 22 without a single amendment. They retained 64m of original cornice and replicated 18m with Hayles & Howe to the point where I can't tell which is which. They restored 18 sashes in situ with Mumford & Wood at the Norwich workshop, kept 15 of the 18 with original Crown glass, and added Selectaglaze secondary glazing that took us from EPC F to EPC C without losing a single pane. The ASHP sits in the rear courtyard at 32 dB(A) — below the WHS limit of 35. We won the Blackheath Society Restoration Award. Historic England put us in the WHS Annual Report. The Country Life feature comes out next month. £1.04M uplift on £612k. Worth every week of the 58-week programme."
— Annabel & Hugo R., Blackheath SE3
Builderr vs other London builders.
The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.
| Criterion | Builderr | Typical London builder | Cowboy outfit |
|---|---|---|---|
| Labour model | Directly employed team (PAYE) | Mixed subcontract gangs | Day-rate cash labour |
| Pricing | Fixed-scope itemised quote | Estimate + provisional sums | Verbal price + variations |
| Design & engineering | In-house architect + SE | Outsourced, separate billing | Builder draws on the back of an envelope |
| Planning + LDC handled | Yes — included in price | Often charged extra | Builder asks you to apply |
| Party wall surveyors | Instructed by us | Your responsibility | Skipped (illegal) |
| Building control | Plans + site inspections booked by us | Building Notice route | Not registered |
| Project management | Dedicated PM, weekly photo updates | Foreman doubles up | Owner-manager juggles 5 jobs |
| Payment schedule | Stage payments against signed-off milestones | Weekly invoices | Cash up front |
| Insurance | £10M PL + 10yr structural warranty | £2–5M PL only | No documented cover |
| Snags at handover | <3 typical | 20–30 typical | Walk-off mid-job common |
| Variation creep | 0% — fixed scope | +15–25% over original quote | +40%+ regularly |
Save £122,400–£275,400 on a heritage whole-house renovation.
Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £612,000.