Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Hackney · E5 · 2026

Double-storey rear + mansard loft, Clapton

Hackney · 1895 Victorian terrace · E5 · 20-week build

Project cost
£192,000
Site programme
20 wks
Type
Loft Conversion
Year
2026

Brief

A late-Victorian (1895) mid-terraced house in Clapton — the clients needed a large open-plan kitchen-diner at ground, a fourth bedroom at first, and a master suite at roof level. All three were delivered in a single permitted development plus full planning application.

Challenge

Hackney requires full planning permission for any double-storey rear extension (PD only allows single-storey rear), and mansard loft conversions are never permitted development because they alter the roof profile beyond Class B limits. The property sits 180m from the Clapton Conservation Area — not formally within the CA, but Hackney's Development Management Policies require material and design quality consistent with the surrounding character. A pre-application meeting with Hackney planning confirmed: London stock brick match, sash-pattern windows to upper floors, and lead-clad mansard cheeks would be required for approval.

Solution

Pre-application advice secured from Hackney's duty planner (cost £360, 3-week turnaround). Architect produced a planning package showing full material match: handmade London stock brick (Bulmer Brick & Tile, BW blend) to double-storey rear, matching the original stock facing. First-floor rear windows — two no. vertical sash in thermally-broken aluminium with narrow sightlines (Kloeber origin profile). Mansard with 72° main pitch, 6mm lead-clad cheeks, and flush Velux rooflights to rear slope. Planning submitted; case officer requested one amendment — chimney pot retention on the party wall stack (structural survey confirmed it was hollow; Builderr retained the pots as feature only). Full planning permission granted 8 weeks after submission. Structurally, two RSJs carry the double-storey rear (6m span, calculated by in-house structural engineer); the mansard steel frame was fabricated off-site and craned in on day 2 of loft works.

Outcome

60m² added across three levels: 19m² kitchen-diner (ground), 19m² bedroom 4 (first), 22m² master suite (mansard). Kitchen-diner has 3m aluminium bifold to garden and 600mm roof lantern over island. Bedroom 4 is south-facing with a Juliet balcony. Mansard master suite has walk-in wardrobe and ensuite with freestanding bath. Building regulations: full plans application, building control sign-off at completion. Property valued at £1.42m post-completion (from £870k before works). Total programme 20 weeks.

Spec

Project specification.

Build
Double-storey rear 19m² per floor + 22m² mansard master suite
Planning
Full planning permission + pre-application advice (Hackney)
Brickwork
Handmade London stock (Bulmer BW blend) — full match to 1895 original
Mansard
72° pitch, lead-clad cheeks, Velux rooflights — steel frame craned in
Structure
2 × RSJ 6m span to double-storey rear; off-site fabricated mansard frame
Windows
Kloeber thermally-broken aluminium vertical sash profile, rear elevation
Building regs
Full plans application — BC signed off at completion
Programme
20 weeks including 8-week pre-application + planning period

Gallery

Inside the build.

Victorian terrace rear elevation Clapton E5
Double-storey rear extension in London stock brick to match the 1895 host building
Mansard loft master bedroom
22m² mansard master suite with lead-clad cheeks and ensuite
Open-plan kitchen-diner ground floor
19m² kitchen-diner with bifolds to garden added by double-storey rear

"We were told a mansard plus double-storey rear in Hackney needed a fight with the planners. Builderr's pre-app meeting meant the planners told us exactly what they wanted and we gave it to them. One minor amendment, then approval. Completely stress-free."

Kofi and Abena Mensah, Clapton E5

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£192,000
a loft conversion · no provisional sums
Typical builder + variations
£230,400
+£38,400 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£278,400
+£86,400 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £38,400£86,400 on a loft conversion.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £192,000.

Want a build like Hackney?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services