Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Hammersmith and Fulham · W6 · 2026

Double-storey rear extension on Edwardian terrace

Hammersmith and Fulham · W6 · Brackenbury Village Conservation Area · 26-week build

Project cost
£248,000
Site programme
26 wks
Type
Double-Storey Rear Extension
Year
2026

Brief

A 4-bed Edwardian terrace in Brackenbury Village (W6) — Article 4 direction zone — needed a major rear addition. The clients wanted a 28m² kitchen extension at ground floor and a 26m² master suite at first floor (over the new ground-floor footprint), plus comprehensive internal reconfiguration. Brackenbury's Article 4 direction removed PD rights — every roof and rear elevation alteration required full planning with conservation officer engagement.

Challenge

Brackenbury Village's Article 4 direction is one of the strictest in inner west London — full planning required for any rear extension, dormers, rooflights, render changes, even window replacement. The H&F conservation team initially resisted a full-height brick double-storey, preferring a single-storey approach. Pre-app submission demonstrated through elevation studies that the double-storey could be approved with: (1) brick first floor stepped back 200mm from ground-floor line, (2) slim-profile Crittall MW40 steel windows in lieu of aluminium, (3) recessed parapet detail at roof line to read as a 'lower-than-ridge' subordinate addition, (4) reclaimed London stock brick survey-matched to the existing terrace, (5) lime mortar joint profile matching the existing.

Solution

Pre-application advice obtained from the H&F Brackenbury conservation officer over a 6-week pre-app process. Full planning submitted with detailed elevation drawings, material specification, sample panel photographs, and Heritage Statement justifying the design. Approved at 13 weeks first-time with three conservation conditions on materials and joinery. Build: 26 weeks. Phase 1 (weeks 1–4): demolition of existing 1970s sun-room and conservatory, structural opening up. Phase 2 (weeks 4–12): foundations, steel structure (3.8 tonnes total — goalpost at ground, beam at first-floor, ridge), masonry to wall-plate. Phase 3 (weeks 12–18): roof, sashes, Crittall installation. Phase 4 (weeks 18–26): internal fit-out — kitchen, ensuite, bathroom, M&E, decoration.

Outcome

Planning approved first-time after pre-app — significant given the Article 4 status. Build delivered in 26 weeks against a 26-week programme. Final floor area increased from 162m² to 216m² (+54m²). Conservation officer attended four site visits during construction and signed off all heritage details on site. Independent valuation uplift £465,000 against £248,000 spend.

Spec

Project specification.

Floor area added
54 sqm (28 sqm ground + 26 sqm first floor)
Article 4 zone
Full planning required; pre-app engagement essential
Heritage brick
5,800 reclaimed London stock survey-matched
Steel structure
3.8 tonnes
Glazing
Crittall MW40 steel + restored timber sashes
Programme
26 weeks site, 11 months total including pre-app and planning

Gallery

Inside the build.

Double-storey rear extension exterior
Rear elevation: full-height brick double-storey with Crittall steel glazing
Open-plan kitchen-diner
Ground-floor kitchen extension with 5m sliding doors
First-floor master with ensuite
First-floor master bedroom with ensuite over kitchen footprint
Crittall steel glazing detail
Crittall MW40 fixed windows and pivot door to garden

"We were told a double-storey extension in Brackenbury would be impossible. Builderr's planning team built the case through pre-app and got it approved first-time. The conservation officer was on site four times during the build to inspect brick joints, sash profiles and slate detailing — they signed off every element. The extension reads as if it were always there."

Felix and Astrid Brennan, Brackenbury Village W6

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£248,000
a double-storey rear extension · no provisional sums
Typical builder + variations
£297,600
+£49,600 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£359,600
+£111,600 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £49,600£111,600 on a double-storey rear extension.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £248,000.

Want a build like Hammersmith and Fulham?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.