Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Hammersmith and Fulham · SW6 · 2026

Victorian master ensuite + family bathroom retrofit — Drummonds + Lefroy Brooks

Hammersmith and Fulham · SW6 Parsons Green · Victorian terrace · 7-week build

Project cost
£68,500
Site programme
7 wks
Type
Bathroom Renovation (master ensuite + family bathroom)
Year
2026

Brief

1894 Victorian terrace in Parsons Green, SW6 — owner-occupier family of four. Two bathrooms in dated 1990s magnolia + chrome condition: a tired 4m² master ensuite off the main bedroom (formerly a third bedroom subdivided) and a 5.5m² family bathroom serving the other two bedrooms. Brief: full strip-out and rebuild of both bathrooms in heritage-luxury spec to match the recently restored ground-floor Victorian features — Drummonds cast-iron baths, Lefroy Brooks Mackintosh aged-brass brassware, Calacatta marble and bespoke fluted-oak vanities. Builderr engaged Q4 2025; site Q1 2026.

Challenge

Three issues. (1) Soil-pipe routing — both bathrooms needed WC and basin relocations of ~1.2m from original positions; the existing 110mm soil pipe ran externally down the rear elevation and needed re-routing internally + boxed in to keep the rear elevation clean (and avoid conservation officer review — this part of Parsons Green is just outside the Parsons Green Conservation Area but visible from it). (2) Cast-iron bath weight — Drummonds Spey 1700mm bath weighs 168kg empty + 320kg filled + occupant = potentially 400kg point load over 4 cast-iron ball-and-claw feet; floor joists needed strengthening in the master ensuite (sister joists doubling) to take the load. (3) Marble specification — Calacatta Tuscan marble is moisture-sensitive; needed sealed-Hydroshield treatment + decoupling membrane + epoxy grout to prevent water-staining + capillary creep over the 25-year design life.

Solution

No planning required (internal works only, not listed). Building Notice route Hammersmith and Fulham Building Control. Build 7 weeks. Weeks 1–2 strip-out both bathrooms + soil-pipe re-routing internally via boxed-in chase + structural joist doubling in master ensuite (sister joists 47×195mm C24 bolted to existing + steel hangers to existing pocket detail). Wet-area waterproofing — Schlüter-KERDI membrane over plywood overlay 18mm marine + bedded in epoxy + KERDI-DRAIN linear drain to walk-in shower. Weeks 3–4 first fix plumbing + electrics. Master ensuite Lefroy Brooks Mackintosh aged-brass thermostatic mixer shower + Drummonds Spey 1700mm cast-iron freestanding bath + bespoke double-basin fluted-oak vanity 1.6m wide with Calacatta Tuscan marble worktop + integrated brass towel rail. Family bathroom Drummonds Cleaver 1700mm freestanding bath + Burlington traditional pillar taps + Burlington high-level WC + bespoke single-basin oak vanity 0.8m wide. Weeks 5–6 finishes. Master ensuite floor + walls Calacatta Tuscan marble 600×600mm sealed Hydroshield + decoupling membrane + epoxy grout; walk-in shower 1.6m × 0.9m with 8mm low-iron glass screen + handmade glazed Bert & May Marble tiles to feature wall. Family bathroom floor encaustic-cement tiles by Bert & May (Sussex range, 200×200mm), walls handmade glazed metro tiles in soft cream + skim plaster + Edward Bulmer Brimstone paint. Underfloor heating throughout both bathrooms (electric mat 200W/m² UFH thermostatically controlled). LED concealed cove lighting + John Cullen brass wall sconces. Heated brass towel rails Drummonds. Week 7 commissioning + Building Control final + snagging + handover.

Outcome

Building Control final certificate issued week 7. Project completed Q1 2026, on programme. Master ensuite uplifted from tired 1990s 4m² magnolia to heritage-luxury hotel-spec wet zone + the family bathroom similarly transformed to spec matching the restored ground floor. Resale agent (Marsh & Parsons Parsons Green) commented bathrooms now match the quality of the £475,000 ground-floor refurb completed 18 months earlier — full house now consistent at top-of-market Parsons Green spec. Estimated combined uplift on bathrooms £95,000 against £68,500 spend = 139% gross ROI on bathroom-only scope. Builderr first Drummonds + Lefroy Brooks Mackintosh pairing + first joist-doubled cast-iron bath retrofit + first project recommended by Drummonds showroom Notting Hill to a direct enquirer. Hammersmith and Fulham 2nd portfolio case study + Parsons Green first.

Spec

Project specification.

Property
1894 Victorian terrace SW6 Parsons Green; outside Parsons Green CA but visible; owner-occupier; previous ground-floor refurb completed Q3 2024 — bathrooms now match that spec
Scope
Full strip-out and rebuild of master ensuite 4m² + family bathroom 5.5m² in heritage-luxury spec; soil-pipe re-routing internally; structural joist doubling for cast-iron bath load
Master ensuite
Drummonds Spey 1700mm cast-iron freestanding bath on Lefroy Brooks Mackintosh ball-and-claw feet (168kg empty / ~400kg loaded); Lefroy Brooks Mackintosh aged-brass thermostatic shower + 8mm low-iron glass screen + handmade Bert & May Marble feature tile wall; bespoke double-basin fluted-oak vanity 1.6m + Calacatta Tuscan marble worktop with integrated brass towel rail
Family bathroom
Drummonds Cleaver 1700mm freestanding bath + Burlington traditional pillar taps + Burlington high-level WC + bespoke single-basin oak vanity 0.8m; encaustic-cement floor tiles Bert & May Sussex 200×200mm; handmade glazed metro wall tiles in cream + Edward Bulmer Brimstone paint
Marble specification
Calacatta Tuscan marble 600×600mm to master ensuite floor + walls; sealed Hydroshield + Schlüter-DITRA decoupling membrane + epoxy grout to prevent water-staining + capillary creep over 25-year design life
Structural
Master ensuite joist doubling — sister joists 47×195mm C24 bolted to existing + steel hangers to existing pocket detail; floor capacity uprated from 1.5kN/m² to 3.0kN/m² to take cast-iron bath point load + occupant
Waterproofing
Schlüter-KERDI membrane over 18mm marine ply overlay bedded in epoxy + KERDI-DRAIN linear drain to walk-in shower + tanked-to-ceiling wet zone
Soil pipe
Existing 110mm soil pipe re-routed from external rear-elevation run to internal boxed chase preserving clean rear elevation; new internal stack vented through roof; Building Control sign-off Part H
Heating + lighting
Electric UFH mat 200W/m² thermostatically controlled both bathrooms; Drummonds brass heated towel rails; LED concealed cove + John Cullen brass wall sconces
Cost + ROI
All-in £68,500 build (master ensuite £39,500 + family bathroom £29,000); estimated combined uplift £95,000 = 139% gross ROI on bathroom-only scope
Programme
7 weeks build (on programme); no planning required; Building Notice route H&F Building Control; Q1 2026 completion
Recognition
First project recommended by Drummonds showroom Notting Hill to direct enquirer Q2 2026; Drummonds case study Q3 2026

Gallery

Inside the build.

Master ensuite freestanding bath
Master ensuite — Drummonds Spey 1700mm cast-iron freestanding bath on Lefroy Brooks Mackintosh ball-and-claw feet; Calacatta Tuscan marble floor
Walk-in shower with brass screens
Master ensuite walk-in shower 1.6m × 0.9m — Lefroy Brooks Mackintosh aged-brass thermostatic shower + 8mm low-iron glass screen + handmade glazed Bert & May Marble tiles
Family bathroom with Drummonds Cleaver bath
Family bathroom — Drummonds Cleaver 1700mm freestanding bath, Burlington traditional taps, encaustic-cement floor tiles by Bert & May
Bespoke vanity unit with Calacatta worktop
Bespoke double-basin vanity 1.6m wide — fluted oak doors, Calacatta Tuscan marble worktop with integrated towel rail, Lefroy Brooks brass taps

"We'd already done the ground floor 18 months earlier with a different contractor + the bathrooms had always been on the next-year list. We'd specified Drummonds + Lefroy Brooks Mackintosh before approaching Builderr — wanted the same hotel-spec feel as the ground floor. Builderr's first-fix detail was the standout for me — joist doubling for the cast-iron bath load, the internal re-routing of the soil pipe so the rear elevation stayed clean, the Schlüter waterproofing under the Calacatta. The marble specification advice (Hydroshield + decoupling + epoxy grout) was the right call — three months in, zero water-staining, zero capillary creep. 7 weeks across two bathrooms with that quality of finish is fast. Drummonds Notting Hill has since sent two prospective clients our way to view the install."

Olivia & Marcus T., Parsons Green SW6

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£68,500
a bathroom renovation (master ensuite + family bathroom) · no provisional sums
Typical builder + variations
£82,200
+£13,700 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£99,325
+£30,825 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £13,700£30,825 on a bathroom renovation (master ensuite + family bathroom).

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £68,500.

Want a build like Hammersmith and Fulham?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.