Haringey · N8 · 2026

Broken-plan kitchen-diner-snug + rear extension, Crouch End

Haringey · 1908 Edwardian semi · N8 · 16-week build

Project cost
£168,000
Site programme
16 wks
Type
House Renovation
Year
2026

Brief

A 1908 Edwardian semi-detached on a tree-lined street in Crouch End — N8, within the Crouch End conservation area. The property had been minimally updated since the 1970s: original mock-Tudor half-timbering on the front gable; original stained-glass front door, hallway side-lights and stair landing window; original pitch-pine parquet throughout the entrance hall and front reception; original cornicing on all ground-floor and first-floor rooms; intact bay windows on both front receptions. Brief: comprehensive heritage restoration of the original features + contemporary broken-plan ground-floor reconfiguration + single-storey rear extension. The clients explicitly asked for broken-plan rather than full open-plan — they wanted a defined kitchen-diner zone visually separated from a quieter snug, both within one connected ground-floor volume.

Challenge

Crouch End conservation area imposes strict controls on front-elevation changes. Article 4 Direction on this section of N8 removed PD rights for rear dormers and roof alterations — a planned hip-to-gable loft extension was deferred to a future phase requiring full planning. The rear extension itself required full planning (4.8m × 5m exceeded the 4m PD depth limit for semi-detached); Haringey Planning required a contemporary, contrasting design (Sapele timber cladding to side wall, zinc-grey standing-seam roof) rather than brick-and-tile pastiche. Inside: original ground-floor layout had separate front reception (3.8m × 4.5m bay), middle reception (3.2m × 3.8m), narrow corridor kitchen (2.4m × 4m). The two reception rooms were structurally separated by a load-bearing internal wall — opening this required a 5m steel beam on twin pad-stones. Heritage: 14 original sash windows (4-over-1 pattern) requiring restoration; original stained-glass panels (5 panels in front door surround and 2 in stair landing) requiring specialist re-leading; original pitch-pine parquet 22m² requiring sand-and-finish.

Solution

Planning: full application submitted; granted 10 weeks first-time after one minor amendment (replacing aluminium rear sliding doors with timber-framed alternative more sympathetic to the Edwardian context). Structural: 5m UB 305×165×40 steel beam installed across the original load-bearing wall between front and middle reception; twin pad-stones at each end; structural opening 4.8m clear. Rear extension structure: 7.5m UB 305×165×46 steel header on rear wall; cavity wall brick perimeter; warm-deck flat roof with 200mm PIR insulation. Broken-plan strategy: the original load-bearing wall removed; a Crittall-style steel screen (Crittall Mondrian range, 2.6m × 2.4m, anthracite frame, clear glass) installed in the position of the original wall to mark the visual zone boundary between snug and kitchen-diner. The Crittall screen has a central pivot door (1.0m wide) allowing acoustic separation when needed and openness when desired. Single 4m × 2.3m aluminium sliding glass wall on the south rear elevation; 1.5m × 2m roof lantern centred over the kitchen island; east-side glazing slot 1.8m × 2.2m bringing dual-aspect morning light. Heritage restoration: 14 sash windows restored by Sash Window Specialists (sash-cord renewal, brass furniture replacement, slim DG retrofit at 11mm Slimlite); 5 stained-glass panels restored by Eclectic Glass over 4 weeks; pitch-pine parquet sanded, walnut-stained, hard-wax oiled (Osmo Polyx-Oil 3032); original cornicing restored across all rooms (Locker & Riley moulds matched to existing intact lengths); 8 original fireplaces decoratively restored. Kitchen: 5m run of bespoke painted-MDF tall units (Farrow & Ball Inchyra Blue, ivory frame) with brass handles (Joseph Giles); 3m island with calacatta-veined quartz top.

Outcome

Floor area added: 24m² (rear extension). Property: 138m² to 162m². Original layout: 5 separated rooms on ground floor → broken-plan: snug (front reception bay retained) + kitchen-diner + utility/boot room. EPC: D (62) → C (74) — sash restoration with slim DG, CWI installation, loft insulation upgrade to 270mm, condensing combi boiler replacement. Heritage retention: all 14 sash windows preserved; all 7 stained-glass panels preserved; all cornicing preserved and restored; pitch-pine parquet preserved and restored; all 8 fireplaces preserved as decorative features. Crouch End conservation officer commended the project at completion. Estate agent valuation post-completion: £1,485,000 (pre-renovation purchase £950,000 + £168,000 spend = £1,118,000; uplift £367,000 net of spend).

Spec

Project specification.

Rear extension
4.8m × 5m (24m²) — sapele timber side wall + zinc standing-seam roof + 4m sliding glass to south garden
Broken-plan
Crittall Mondrian 2.6m × 2.4m anthracite steel screen with central pivot door — defines snug/kitchen-diner zones in connected volume
Heritage windows
14 sash windows restored + slim DG retrofit (Slimlite 11mm); 7 stained-glass panels restored
Parquet
22m² original pitch-pine — sanded, walnut-stained, Osmo hard-wax oil finished
EPC
D (62) → C (74) — CWI + sash slim DG + loft upgrade + new combi boiler
Planning
Full planning (Crouch End CA + rear depth >4m) — 10 weeks, 1 amendment
Programme
16 weeks build, 28 weeks total

Gallery

Inside the build.

Broken plan kitchen diner snug Crouch End Edwardian N8 Haringey
Broken-plan ground floor: Crittall steel screen with central pivot door separates kitchen-diner from snug — single connected volume read as two distinct zones
Single storey rear extension Crouch End Edwardian semi N8
Single-storey rear extension (4.8m × 5m, 24m²) with 4m sliding glass to east-facing garden
Restored Edwardian stained glass hallway Crouch End N8
Original Edwardian stained-glass front door, hallway side-lights and landing window — restored panel-by-panel by Eclectic Glass over 4 weeks
Restored parquet floor Edwardian Crouch End
Original pitch-pine parquet — sanded, walnut-stained, hard-wax oil finished

"We wanted the heritage to feel preserved, not preserved-in-aspic — and the modern intervention at the rear to be confident, not apologetic. The Crittall screen between kitchen and snug is the single best decision in the whole project. The restored parquet and stained glass make us notice the house every single day."

Catherine and James Whitfield, Crouch End N8

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£168,000
a house renovation · no provisional sums
Typical builder + variations
£201,600
+£33,600 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£243,600
+£75,600 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £33,600£75,600 on a house renovation.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £168,000.