Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Haringey · N6 · 2026

Highgate Edwardian circular-economy retrofit

Haringey · 1908 Edwardian terrace N6 · 22-week build · WLCA + reclaimed materials + low-carbon spec

Project cost
£295,000
Site programme
22 wks
Type
Whole-House Renovation + Side Return
Year
2026

Brief

1908 Edwardian end-of-terrace N6 Highgate — 156m² over 3 storeys, Highgate Conservation Area, Article 4 Direction restricting front-elevation alteration. Owners (climate scientist + furniture designer + 2 children) brief: full house renovation including new 18m² side return, demonstrating circular-economy + low-carbon principles end-to-end — Whole-Life Carbon Assessment (WLCA) per RICS PS 2023 with quantified embodied carbon reduction target ≥35% vs conventional spec; reclaimed materials wherever feasible (brick, timber, fittings); natural insulation (Steico wood-fibre, sheep wool) replacing all petroleum-based foams; lime plaster + natural paints throughout heritage rooms; GGBS-replacement concrete (CEM III/A) for foundations; FSC/PEFC structural timber; design-for-disassembly (mechanical fix, no glue) for kitchen + joinery. Budget £295,000 (£1,890/m²). Side return planning + LBC-equivalent CA consent. Children's air-quality + breathable-fabric major driver alongside carbon.

Challenge

Six compounding constraints. (1) Conservation Area + Article 4 — front elevation untouchable (no PV on front roof; original sash retained); side + rear conditioned (heritage materials match). Planning + Heritage Statement by IHBC consultant (Heritage Collective). (2) Embodied carbon target — pre-design WLCA showed conventional spec 442 kgCO2e/m²; 35% reduction target = ≤287 kgCO2e/m². Required material substitution at every line of bill of quantities. (3) Reclaimed brick supply — needed 8,400 bricks matching London yellow stock; LASSCO Three Mills had 5,200 in stock; Cawarden Reclaim sourced additional 3,200 with 8-week lead — ordering at concept stage to lock supply. (4) Wood-fibre insulation U-value — Steico Flex 140mm achieves U-value 0.20 W/m²K vs PIR 100mm at 0.18; design accommodated 40mm extra wall thickness internally (lost 1.2m² floor area). (5) Lime plaster slow set + skilled labour — 5 lime plasterers in London competent for full-house spec; book 12 weeks ahead; 30-day cure between coats added 6 weeks vs gypsum programme. (6) GGBS concrete + winter pour — CEM III/A foundation pour week 3 in 4°C ambient required Sika ViscoCrete admixture + thermal blankets for 7-day cure. Project ran October–March winter programme.

Solution

Pre-design + WLCA + consents 16 weeks. WLCA by Targeting Zero (RICS PS 2023 method, One Click LCA tool) — conventional spec baseline 442 kgCO2e/m² × 174m² post-extension = 76,900 kgCO2e A1–A5; target spec 287 kgCO2e/m² × 174m² = 49,940 kgCO2e (–35%). Planning + Heritage Statement submitted week 8; approved week 16 zero amendments. CE Statement prepared voluntarily — quantified retention (94% existing structure retained), waste hierarchy targets (88% diversion-from-landfill via 5-bin sort), reclaimed quantities (8,400 bricks + 84m timber joinery + 12 doors + 6 fireplaces). Build 22 weeks. Foundations weeks 1–3: trench foundation CEM III/A concrete (50% GGBS replacement) — 6.8m³ at 0.45 kgCO2e/kg vs CEM I 0.95 = 17,200 kgCO2e saved on substructure alone; winter pour with Sika ViscoCrete + 5-day insulated cure. Side return walls weeks 4–7: reclaimed London yellow stock brick (8,400 bricks at 0.005 kgCO2e/brick vs new 0.21 = 1,700 kgCO2e saved); NHL 3.5 lime mortar (carbonating — net-negative over 5 years); 100mm Steico Flex wood-fibre cavity insulation. Roof weeks 8–10: existing roof retained + 200mm sheep wool insulation between/over rafters (Black Mountain UK, 95% recycled fibre); reclaimed Welsh slate via SalvoWeb. Internal weeks 11–22: Steico Flex 80mm IWI to external walls of heritage rooms (preserving sash reveals + cornices); lime plaster to heritage rooms (NHL 2 base + finish by SPAB-affiliated plasterer); gypsum to side-return + kitchen + bathrooms for speed; Edward Bulmer natural paint heritage rooms; Little Greene Intelligent low-VOC modern rooms; reclaimed pitch pine flooring (MASS Camberwell); 4 reclaimed Victorian cast-iron fireplaces (LASSCO Brunswick House + Drummonds); deVOL mechanical-fix kitchen (bolt-on plinths + screw-down worktop — design-for-disassembly); reclaimed brass ironmongery (Willow & Stone); ASHP 7kW Vaillant aroTHERM Plus replacing gas boiler (BUS £7,500 grant); MVHR Zehnder ComfoAir; 3.2kWp Sunology PV rear roof only (Article 4 restricts front). Final WLCA week 22: measured 271 kgCO2e/m² × 174m² = 47,150 kgCO2e — 38.7% below conventional baseline, exceeded 35% target.

Outcome

WLCA verified 271 kgCO2e/m² A1–A5 — 38.7% below conventional baseline (29,750 kgCO2e A1–A5 saved). CE Statement metrics: 94% structure retention; 88% waste diversion from landfill; 8,400 reclaimed bricks + 84m reclaimed timber + 12 reclaimed doors + 6 reclaimed fireplaces; 100% natural insulation (no PIR/PUR); 100% lime plaster + natural paint heritage rooms; 100% FSC/PEFC structural timber. Operational: EPC E (51) → B (84); heating cost £2,400/year → £580/year (£1,820 saved annually); CO2 in operation 4,200 → 480 kgCO2e/year. Property valuation pre £1.18M → post £1.62M (£440k uplift on £295k spend net of £7,500 BUS grant = 152% gross ROI). Featured: AECB CarbonLite Retrofit Awards 2026 finalist; LETI Retrofit Showcase 2026; Passive House Plus magazine November 2026 issue ('Circular Edwardian' cover feature); RIBA London Awards 2027 shortlist (Sustainability Award category). Builderr first formal WLCA-quantified circular-economy case study + first reclaimed-brick + lime-plaster + sheep-wool + GGBS-concrete combined retrofit. Haringey borough now 2 portfolio case studies; Highgate N6 first project. Featured Targeting Zero + RICS WLCA Best Practice 2027 case database.

Spec

Project specification.

WLCA result
271 kgCO2e/m² A1–A5 — 38.7% below conventional baseline 442 kgCO2e/m² (target ≥35%) — Targeting Zero / One Click LCA / RICS PS 2023 method
Embodied carbon savings
29,750 kgCO2e A1–A5 avoided — equivalent to ~58 transatlantic return flights or ~14 years of average UK household operational carbon
Substructure
CEM III/A concrete (50% GGBS) 6.8m³ — 17,200 kgCO2e saved on substructure vs CEM I — Aggregate Industries Ecocrete supply
Side return walls
8,400 reclaimed London yellow stock brick (LASSCO Three Mills + Cawarden Reclaim) — NHL 3.5 lime mortar — 100mm Steico Flex wood-fibre cavity insulation
Insulation
Steico Flex wood-fibre 80mm IWI heritage rooms + 100mm cavity new walls + 200mm sheep wool (Black Mountain) loft — zero PIR/PUR throughout
Roofing
Existing roof structure 100% retained; reclaimed Welsh Penrhyn slate via SalvoWeb for repairs; sheep wool insulation between/over rafters
Internal finishes
Lime plaster (NHL 2) throughout heritage rooms + Edward Bulmer natural paint zero-VOC; gypsum + Little Greene Intelligent low-VOC modern rooms
Joinery + fittings
Reclaimed pitch pine flooring (MASS); 4 reclaimed Victorian cast-iron fireplaces (LASSCO + Drummonds); 12 reclaimed period doors + brass ironmongery (Willow & Stone)
Kitchen
deVOL bespoke mechanically-fixed (no glue) — fully demountable for future reuse — bolt-on plinths + screw-down worktop — design-for-disassembly principle
Heating
Vaillant aroTHERM Plus 7kW ASHP replacing gas boiler — BUS grant £7,500 — wet UFH side return + radiator retrofit heritage rooms (preserve cornice + skirting)
Ventilation + PV
Zehnder ComfoAir MVHR (heat recovery 88%); 3.2kWp Sunology PV rear roof only (Article 4 restricts front roof) — SEG Smart Export Guarantee
EPC + operational
EPC E (51) → B (84); heating cost £2,400/year → £580/year; operational CO2 4,200 → 480 kgCO2e/year
Waste diversion
88% diversion from landfill via 5-bin segregated skip (brick → reclaim, timber → reclaim/biomass, metal → scrap, plaster → recycle, residual)
Structural retention
94% existing structure retained — all loadbearing brick walls; all original floor + ceiling joists; all original sashes (restored); all cornices + ceiling roses + skirting
Programme
22 weeks build + 16 weeks pre-design + WLCA + CA planning + Heritage Statement = 38 weeks total
Awards + features
AECB CarbonLite Retrofit Awards finalist; LETI Retrofit Showcase; Passive House Plus November 2026 cover feature; RIBA London Awards 2027 shortlist (Sustainability)
Property value
£1.18M → £1.62M (+£440k on £295k spend net of £7,500 BUS grant — 152% gross ROI)

Gallery

Inside the build.

Highgate Edwardian terrace N6 circular retrofit
1908 Edwardian terrace N6 Highgate — full WLCA + circular-economy retrofit + side return — 295k spend EPC E→B — 22-week build
Reclaimed London stock brick side return
Side return outer leaf — reclaimed London yellow stock brick from LASSCO Three Mills + Cawarden Reclaim — 8,400 bricks at 95% lower embodied carbon vs new
Wood-fibre Steico insulation Highgate
Steico Flex 140mm wood-fibre insulation to rear wall + roof — μ 1–2 vapour-open + 380 kgCO2e/m³ vs PIR 1,200 kgCO2e/m³ — 68% embodied carbon reduction
Edward Bulmer lime paint Highgate
Lime plaster + Edward Bulmer natural paint throughout heritage rooms — zero VOC + breathable + carbon-sequestering lime carbonation over 20-year life

"We briefed Builderr for a circular-economy + low-carbon retrofit that could stand up to formal WLCA scrutiny — both of us work professionally adjacent to climate (I'm at Imperial Climate Centre, she designs furniture from reclaimed timber). We needed proof, not greenwash. Targeting Zero's verified WLCA showed 38.7% embodied carbon below baseline — 29,750 kgCO2e saved on a single house. Reclaimed brick supply came together because Builderr ordered at concept stage rather than tender; lime plaster ran 6 weeks longer than gypsum but the heritage rooms feel measurably different — humidity 45–55% steady, no condensation, the air quality our kids breathe is the best in the school cohort tested by their teacher's environmental project. Edward Bulmer paint colour palette far exceeds Farrow & Ball depth. £295k spend on a £1.18M house added £440k value + an unexpected feature in Passive House Plus + AECB finalist + RIBA shortlist. The CE Statement Builderr prepared voluntarily (single dwelling, not strategic) is the strongest planning narrative I have read on a residential project."

Dr Anjali + Marcus Sterling-Okonkwo, Highgate N6

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£295,000
a whole-house renovation + side return · no provisional sums
Typical builder + variations
£354,000
+£59,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£427,750
+£132,750 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £59,000£132,750 on a whole-house renovation + side return.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £295,000.

Want a build like Haringey?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services