Highgate Edwardian circular-economy retrofit
Haringey · 1908 Edwardian terrace N6 · 22-week build · WLCA + reclaimed materials + low-carbon spec
Brief
1908 Edwardian end-of-terrace N6 Highgate — 156m² over 3 storeys, Highgate Conservation Area, Article 4 Direction restricting front-elevation alteration. Owners (climate scientist + furniture designer + 2 children) brief: full house renovation including new 18m² side return, demonstrating circular-economy + low-carbon principles end-to-end — Whole-Life Carbon Assessment (WLCA) per RICS PS 2023 with quantified embodied carbon reduction target ≥35% vs conventional spec; reclaimed materials wherever feasible (brick, timber, fittings); natural insulation (Steico wood-fibre, sheep wool) replacing all petroleum-based foams; lime plaster + natural paints throughout heritage rooms; GGBS-replacement concrete (CEM III/A) for foundations; FSC/PEFC structural timber; design-for-disassembly (mechanical fix, no glue) for kitchen + joinery. Budget £295,000 (£1,890/m²). Side return planning + LBC-equivalent CA consent. Children's air-quality + breathable-fabric major driver alongside carbon.
Challenge
Six compounding constraints. (1) Conservation Area + Article 4 — front elevation untouchable (no PV on front roof; original sash retained); side + rear conditioned (heritage materials match). Planning + Heritage Statement by IHBC consultant (Heritage Collective). (2) Embodied carbon target — pre-design WLCA showed conventional spec 442 kgCO2e/m²; 35% reduction target = ≤287 kgCO2e/m². Required material substitution at every line of bill of quantities. (3) Reclaimed brick supply — needed 8,400 bricks matching London yellow stock; LASSCO Three Mills had 5,200 in stock; Cawarden Reclaim sourced additional 3,200 with 8-week lead — ordering at concept stage to lock supply. (4) Wood-fibre insulation U-value — Steico Flex 140mm achieves U-value 0.20 W/m²K vs PIR 100mm at 0.18; design accommodated 40mm extra wall thickness internally (lost 1.2m² floor area). (5) Lime plaster slow set + skilled labour — 5 lime plasterers in London competent for full-house spec; book 12 weeks ahead; 30-day cure between coats added 6 weeks vs gypsum programme. (6) GGBS concrete + winter pour — CEM III/A foundation pour week 3 in 4°C ambient required Sika ViscoCrete admixture + thermal blankets for 7-day cure. Project ran October–March winter programme.
Solution
Pre-design + WLCA + consents 16 weeks. WLCA by Targeting Zero (RICS PS 2023 method, One Click LCA tool) — conventional spec baseline 442 kgCO2e/m² × 174m² post-extension = 76,900 kgCO2e A1–A5; target spec 287 kgCO2e/m² × 174m² = 49,940 kgCO2e (–35%). Planning + Heritage Statement submitted week 8; approved week 16 zero amendments. CE Statement prepared voluntarily — quantified retention (94% existing structure retained), waste hierarchy targets (88% diversion-from-landfill via 5-bin sort), reclaimed quantities (8,400 bricks + 84m timber joinery + 12 doors + 6 fireplaces). Build 22 weeks. Foundations weeks 1–3: trench foundation CEM III/A concrete (50% GGBS replacement) — 6.8m³ at 0.45 kgCO2e/kg vs CEM I 0.95 = 17,200 kgCO2e saved on substructure alone; winter pour with Sika ViscoCrete + 5-day insulated cure. Side return walls weeks 4–7: reclaimed London yellow stock brick (8,400 bricks at 0.005 kgCO2e/brick vs new 0.21 = 1,700 kgCO2e saved); NHL 3.5 lime mortar (carbonating — net-negative over 5 years); 100mm Steico Flex wood-fibre cavity insulation. Roof weeks 8–10: existing roof retained + 200mm sheep wool insulation between/over rafters (Black Mountain UK, 95% recycled fibre); reclaimed Welsh slate via SalvoWeb. Internal weeks 11–22: Steico Flex 80mm IWI to external walls of heritage rooms (preserving sash reveals + cornices); lime plaster to heritage rooms (NHL 2 base + finish by SPAB-affiliated plasterer); gypsum to side-return + kitchen + bathrooms for speed; Edward Bulmer natural paint heritage rooms; Little Greene Intelligent low-VOC modern rooms; reclaimed pitch pine flooring (MASS Camberwell); 4 reclaimed Victorian cast-iron fireplaces (LASSCO Brunswick House + Drummonds); deVOL mechanical-fix kitchen (bolt-on plinths + screw-down worktop — design-for-disassembly); reclaimed brass ironmongery (Willow & Stone); ASHP 7kW Vaillant aroTHERM Plus replacing gas boiler (BUS £7,500 grant); MVHR Zehnder ComfoAir; 3.2kWp Sunology PV rear roof only (Article 4 restricts front). Final WLCA week 22: measured 271 kgCO2e/m² × 174m² = 47,150 kgCO2e — 38.7% below conventional baseline, exceeded 35% target.
Outcome
WLCA verified 271 kgCO2e/m² A1–A5 — 38.7% below conventional baseline (29,750 kgCO2e A1–A5 saved). CE Statement metrics: 94% structure retention; 88% waste diversion from landfill; 8,400 reclaimed bricks + 84m reclaimed timber + 12 reclaimed doors + 6 reclaimed fireplaces; 100% natural insulation (no PIR/PUR); 100% lime plaster + natural paint heritage rooms; 100% FSC/PEFC structural timber. Operational: EPC E (51) → B (84); heating cost £2,400/year → £580/year (£1,820 saved annually); CO2 in operation 4,200 → 480 kgCO2e/year. Property valuation pre £1.18M → post £1.62M (£440k uplift on £295k spend net of £7,500 BUS grant = 152% gross ROI). Featured: AECB CarbonLite Retrofit Awards 2026 finalist; LETI Retrofit Showcase 2026; Passive House Plus magazine November 2026 issue ('Circular Edwardian' cover feature); RIBA London Awards 2027 shortlist (Sustainability Award category). Builderr first formal WLCA-quantified circular-economy case study + first reclaimed-brick + lime-plaster + sheep-wool + GGBS-concrete combined retrofit. Haringey borough now 2 portfolio case studies; Highgate N6 first project. Featured Targeting Zero + RICS WLCA Best Practice 2027 case database.
Spec
Project specification.
Gallery
Inside the build.
"We briefed Builderr for a circular-economy + low-carbon retrofit that could stand up to formal WLCA scrutiny — both of us work professionally adjacent to climate (I'm at Imperial Climate Centre, she designs furniture from reclaimed timber). We needed proof, not greenwash. Targeting Zero's verified WLCA showed 38.7% embodied carbon below baseline — 29,750 kgCO2e saved on a single house. Reclaimed brick supply came together because Builderr ordered at concept stage rather than tender; lime plaster ran 6 weeks longer than gypsum but the heritage rooms feel measurably different — humidity 45–55% steady, no condensation, the air quality our kids breathe is the best in the school cohort tested by their teacher's environmental project. Edward Bulmer paint colour palette far exceeds Farrow & Ball depth. £295k spend on a £1.18M house added £440k value + an unexpected feature in Passive House Plus + AECB finalist + RIBA shortlist. The CE Statement Builderr prepared voluntarily (single dwelling, not strategic) is the strongest planning narrative I have read on a residential project."
— Dr Anjali + Marcus Sterling-Okonkwo, Highgate N6
Builderr vs other London builders.
The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.
| Criterion | Builderr | Typical London builder | Cowboy outfit |
|---|---|---|---|
| Labour model | Directly employed team (PAYE) | Mixed subcontract gangs | Day-rate cash labour |
| Pricing | Fixed-scope itemised quote | Estimate + provisional sums | Verbal price + variations |
| Design & engineering | In-house architect + SE | Outsourced, separate billing | Builder draws on the back of an envelope |
| Planning + LDC handled | Yes — included in price | Often charged extra | Builder asks you to apply |
| Party wall surveyors | Instructed by us | Your responsibility | Skipped (illegal) |
| Building control | Plans + site inspections booked by us | Building Notice route | Not registered |
| Project management | Dedicated PM, weekly photo updates | Foreman doubles up | Owner-manager juggles 5 jobs |
| Payment schedule | Stage payments against signed-off milestones | Weekly invoices | Cash up front |
| Insurance | £10M PL + 10yr structural warranty | £2–5M PL only | No documented cover |
| Snags at handover | <3 typical | 20–30 typical | Walk-off mid-job common |
| Variation creep | 0% — fixed scope | +15–25% over original quote | +40%+ regularly |
Save £59,000–£132,750 on a whole-house renovation + side return.
Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £295,000.
Want a build like Haringey?
Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services
More projects