Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Harrow · HA7 · 2026

1968 detached deep retrofit — EnerPHit, EPC G→A+, net energy positive

Harrow · 1968 detached · HA7 Stanmore · 28-week build

Project cost
£348,000
Site programme
28 wks
Type
Whole House
Year
2026

Brief

1968 4-bed detached HA7 Stanmore — 198m² over 2 storeys + integral garage, 480m² plot, original solid-brick + ventilated cavity construction (poorly insulated), original metal-frame Crittall single-glazing failed, asbestos roof tiles end-of-life, original oil-fired heating decommissioned. EPC G (28) — among bottom 5% of London housing stock. Owners (PhD academic + sustainability consultant + 2 young children) brief: certified EnerPHit retrofit (Passivhaus retrofit standard) — net energy positive — EPC A+ target — all-electric, GSHP, MVHR, comprehensive fabric upgrade including external wall insulation, triple glazing, airtightness 1.0 m³/h/m² @50Pa target, 8.4 kWp PV array + 13.5 kWh battery. Budget £348,000. PAS 2035 + EnerPHit dual certification. 60-week total programme.

Challenge

Six compounding constraints. (1) EnerPHit certification ambition: airtightness 1.0 m³/h/m² @50Pa, U-values <0.15 W/m²K on opaque elements, triple glazing Uw <0.85, MVHR heat recovery >82%, certified Passivhaus designer required. Achieving on existing single-leaf brick 1968 fabric requires comprehensive EWI 180mm Kingspan K15 + airtightness membrane + replacement windows + replacement floor build-up + new airtight roof. (2) Asbestos roof tiles end-of-life requiring HSE-licensed removal £14,500. (3) GSHP feasibility: front garden 280m² adequate for 2× 110m vertical boreholes; Environment Agency notification required. (4) Crittall single-glazing replacement: 21 windows + 3 doors — Internorm HF410 timber-alu triple-glazed in matching profiles — £58,500 supply + £18,500 install. (5) Heat loss calculation: pre-retrofit 18.8 kW; post-retrofit 4.2 kW design temp — GSHP sized 12kW; radiators all replaced (eliminated) for full UFH retrofit. (6) PAS 2035 + EnerPHit dual certification with retrofit coordinator + Passivhaus designer (Architype, BRE-certified) from RIBA Stage 1.

Solution

Pre-design + consents 32 weeks. EnerPHit feasibility; PAS 2035 coordinator engaged; Passivhaus designer Architype Architects appointed; MCS heat loss + GSHP feasibility; Environment Agency borehole notification; Building Regulations submission with EnerPHit junction details; BUS + ECO4 + Smart Export Guarantee applications. Build Phase 1 weeks 1–14 fabric upgrade. Asbestos roof tile removal HSE-licensed weeks 1–4 (£14,500); new clay tile roof + 300mm Kingspan K7 in joist void + 150mm K12 above ceiling (warm roof). EWI: 180mm Kingspan K15 to all walls + brick slip finish matching original London Stock + airtightness membrane Pro Clima Intello Plus continuous around envelope. Floor build-up: lifted slab + 200mm Kingspan TF70 + 80mm liquid screed with UFH + airtightness membrane joined to wall membrane. Windows: 21 windows + 3 doors Internorm HF410 triple-glazed; passive-house-grade install tapes; intermediate airtightness test week 12 measured 1.2 m³/h/m² — additional taping at 3 weak junctions; retest week 14 0.92 m³/h/m². Build Phase 2 weeks 15–28 services. GSHP: 2× 110m vertical boreholes drilled in front garden (4-day specialist rig); Mitsubishi Ecodan ground-source 12kW + 300L pre-plumbed cylinder; flow 35°C UFH throughout (full UFH retrofit ground + first floor — no radiators retained); Heatmiser NeoHub multi-zone control 9 zones. MVHR: Zehnder ComfoAir Q600 sized for EnerPHit; semi-rigid 90mm radial ducting through new dropped ceiling zone; commissioned at 96 L/s; measured heat recovery 91% (EnerPHit 82% target exceeded). PV array: 8.4 kWp Solitek monocrystalline (24× 350W) on south-facing rear roof; 13.5 kWh Tesla Powerwall 3 battery; SolarEdge optimisers per panel; Smart Export Guarantee 15p/kWh. Final airtightness test week 28: 0.88 m³/h/m² @50Pa (exceeds EnerPHit 1.0). EnerPHit certification submitted BRE; certified post-construction week 32.

Outcome

Certified EnerPHit retrofit — BRE certification issued week 32. EPC G (28) → A+ (102) — among top 0.1% of UK existing housing stock; A+ band rare in retrofit. Heating bill: pre-retrofit £4,800/year (oil + electric); post-retrofit £450/year all-electric net of PV export earnings (post-retrofit electricity consumption 2,800 kWh/year; PV generation 7,400 kWh/year; battery self-consumption 88%; net export ~3,500 kWh × 15p = £525 SEG payment annually). Net energy positive: £75/year. Net carbon: pre-retrofit 12,800 kgCO2/year; post-retrofit ~0 kgCO2/year (net-zero in operation). MVHR measured CO2 average 480 ppm; humidity 42–55% stable; airtightness 0.88 m³/h/m² @50Pa. GSHP SCOP measured 4.42 (predicted 4.2 exceeded). Building Control completion week 29; PAS 2035 + EnerPHit dual certification complete week 32. Property valuation: pre-renovation £1.4M; post-renovation £1.92M (£520,000 uplift on £348,000 net spend after grants £14,800 — 156% gross ROI). Featured in Passive House Plus magazine cover July 2026; submitted to AECB Carbonlite Awards; case study material for Passivhaus Trust + Retrofit Academy. Builderr first EnerPHit certified project. Harrow borough portfolio now 3 case studies (Pinner, Hampstead Garden Suburb-adjacent, Stanmore).

Spec

Project specification.

Certification
BRE-certified EnerPHit (Passivhaus retrofit standard) + PAS 2035 dual certification
Airtightness
Final test 0.88 m³/h/m² @50Pa — significantly exceeds EnerPHit 1.0 target
EWI
180mm Kingspan K15 to all walls + brick slip matching London Stock + Pro Clima Intello Plus airtightness membrane continuous
Glazing
21 windows + 3 doors Internorm HF410 triple-glazed timber-alu (Ug 0.5, Uw 0.78) + passive-house install tapes
Roof
Asbestos tiles removed HSE-licensed; new clay tile + 300mm K7 in void + 150mm K12 above ceiling (warm roof)
Floor
Lifted slab + 200mm TF70 + 80mm screed + UFH + airtightness membrane joined to walls
GSHP
Mitsubishi Ecodan ground-source 12kW + 2× 110m vertical boreholes + 300L cylinder; SCOP measured 4.42
MVHR
Zehnder ComfoAir Q600; 96 L/s commissioned; heat recovery measured 91% (EnerPHit 82% target exceeded)
PV + battery
8.4 kWp Solitek + 13.5 kWh Tesla Powerwall 3 + SolarEdge optimisers; 88% self-consumption + SEG export
Heating
Wet UFH throughout ground + first floor (no radiators) at 35°C; Heatmiser NeoHub 9 zones
EPC
G (28) → A+ (102) — top 0.1% UK housing stock
Energy balance
Net energy positive — £450/year heating import offset by £525/year SEG export = net positive £75/year
Carbon
12,800 kgCO2/year → ~0 kgCO2/year operation; embodied retrofit ~25,000 kgCO2 amortised over 60 years
Grants
BUS £7,500 (GSHP eligible) + ECO4 £7,300 = £14,800
Property value
£1.4M → £1.92M (+£520k on £348k spend net of grants — 156% gross ROI)
Programme
28 weeks build + 32 weeks pre-design + certification = 60 weeks total

Gallery

Inside the build.

Harrow Stanmore 1968 detached deep retrofit EnerPHit HA7
1968 detached HA7 Stanmore — EnerPHit-grade deep retrofit — EPC G (28) → A+ (102) — net energy positive with 8.4 kWp PV + 13.5 kWh battery
External wall insulation EWI K15 Harrow Stanmore
180mm Kingspan K15 EWI to all external walls — matching brick slip finish — U-value 0.13 W/m²K — air tightness 0.88 m³/h/m² @50Pa
GSHP borehole installation Harrow HA7
GSHP 12kW with 2× 110m vertical boreholes — front-garden install — SCOP measured 4.42 — Environment Agency notification compliant
Triple glazing Internorm HF410 Harrow Stanmore
Internorm HF410 timber-alu triple-glazed throughout — 21 windows + 3 doors — Ug 0.5 W/m²K — passive-house grade install tapes throughout

"We bought a 1968 detached with EPC G — among the worst-performing houses in London — and asked Builderr to deliver an EnerPHit certified retrofit. No one we spoke to in Harrow had attempted EnerPHit before. Builderr engaged Architype as Passivhaus designer, BRE as certifier, MCS for ground-source design, and committed to the airtightness target from week one. The result: 0.88 m³/h/m² airtightness against a 1.0 target, EPC G to A+, net energy positive operation with the PV + battery. Heating bills are essentially zero — the SEG export covers the import. The house is silent, stable, completely free of draughts and condensation. The indoor air quality measurement of 480 ppm CO2 is materially better than the schools the children attend. £348k spend (£334k net of grants), £520k value uplift, BRE EnerPHit certification, and a Passive House Plus cover. Worth every week of the 32-week pre-design phase."

Prof. Eleanor and James Whitfield, Stanmore HA7

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£348,000
a whole house · no provisional sums
Typical builder + variations
£417,600
+£69,600 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£504,600
+£156,600 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £69,600£156,600 on a whole house.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £348,000.

Want a build like Harrow?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services