Wraparound side-rear extension + dormer loft, Romford
Havering · 1962 semi-detached · RM2 · 20-week build
Brief
A 1962 brick-and-render semi-detached in Gidea Park, Romford — RM2, not in a conservation area, PD rights intact (Havering is one of London's most PD-friendly outer boroughs). The clients (couple with three children) had outgrown the 96m² 3-bed layout and wanted a 4-bed family home with a large kitchen-diner. The 3m side return and 9m rear garden depth allowed a wraparound single-storey extension plus a rear dormer loft conversion as a combined project. Total budget: £168,000. Havering borough first case study for the Builderr portfolio.
Challenge
Three constraints shaped the design. (1) PD wraparound compliance — combined side and rear elements straddle two PD classes (Class A side + Class A rear with Larger Home Extension Prior Approval). Builderr submitted a single Lawful Development Certificate plus Prior Approval for the rear 4.8m projection. LDC granted at 8 weeks; Prior Approval granted at 7 weeks (no neighbour objections during 21-day consultation). (2) Drainage and soakaways — London Clay site with BRE Digest 365 infiltration rate of 8mm/hour (borderline acceptable). Building Control accepted a modified soakaway with overflow to the existing surface-water drain into the Havering Council adopted highway drain. (3) Loft head height — existing loft ridge 2.55m, eaves 1.6m — marginal for habitable conversion. Solution: rear dormer with 2.4m internal head height across the full new dormer footprint (8m × 4m). Dormer volume 80m³ exceeded the 50m³ Class B PD allowance for a semi, so full planning was required (granted at 9 weeks). Existing 1980s side-return lean-to had an asbestos-cement roof requiring HSE-licensed abatement (£2,800 specialist contractor budget line).
Solution
Phased programme: family in residence weeks 1–8 (loft only, accessed via external scaffold staircase), then vacated weeks 9–20 (ground-floor wraparound + first-floor remodel). Phase 1 — loft: existing roof opened internally, new 175mm joist floor with acoustic underlay; rear dormer 8m × 4m flat-roof timber-frame construction with EPDM warm deck and zinc cladding to front face; 2× Velux GGL UK10 to front pitched slope; new staircase from first-floor landing (winder-foot configuration); master 16m² + en-suite 5m² + walk-in wardrobe 3m². Phase 2 — wraparound: 1980s asbestos-roofed lean-to abated by HSE-licensed contractor; new strip footings 600mm × 1.0m on London Clay; 178×102 UB steel beam at junction of existing rear wall and new extension; 38m² ground-floor addition (kitchen 18m², diner 12m², family/snug 8m²) open-plan with 4.2m × 2.1m Reynaers CF 77 bifolds (anthracite grey, flush threshold) and 1.5m × 1.5m Glazing Vision roof lantern above the dining table; integrated boot room (3m²) off the side entrance from the driveway. First-floor remodel: ensuite added to second bedroom; family bathroom refurbished; airing cupboard relocated. Heating: 2008 Worcester combi decommissioned; new Vaillant ecoTEC plus 38kW combi installed in utility room; 14 new radiators (heat-pump-ready sized for 50°C flow); wet UFH to ground-floor extension only.
Outcome
Floor area added: 62m² (38m² wraparound ground floor + 24m² dormer loft). Property uplifted from 96m² 3-bed/1-bath to 158m² 4-bed/2.5-bath. Side-return 1980s lean-to (16m² of low-quality, asbestos-roofed cold space) demolished and replaced; net habitable floor area gain 46m² after demolition. EPC: D (62) → C (76) — new extension to Part L 2025; loft insulation top-up to 350mm; new boiler. Build delivered in 20 weeks within programme (8 weeks Phase 1 + 12 weeks Phase 2); final spend £172,400 against £168,000 budget (2.6% over due to asbestos abatement contingency). Romford market: pre-renovation valuation £475,000; post-renovation £685,000 (£210,000 gross value uplift on £172,400 build cost — 22% ROI). Havering Council Building Control completion certificate issued at week 21.
Spec
Project specification.
Gallery
Inside the build.
"Builderr handled the asbestos abatement and the wraparound PD route without us having to think about it. The two-phase programme meant we kept the kids in school through the loft phase and only relocated for the messy ground-floor works. Romford isn't where most architects want to work but Builderr's team treated this like a Hampstead job — full design service, proper drawings, proper site team. £685k valuation on a Gidea Park semi is genuinely good for the area."
— Lisa and Chris Whitmore, Gidea Park RM2
Builderr vs other London builders.
The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.
| Criterion | Builderr | Typical London builder | Cowboy outfit |
|---|---|---|---|
| Labour model | Directly employed team (PAYE) | Mixed subcontract gangs | Day-rate cash labour |
| Pricing | Fixed-scope itemised quote | Estimate + provisional sums | Verbal price + variations |
| Design & engineering | In-house architect + SE | Outsourced, separate billing | Builder draws on the back of an envelope |
| Planning + LDC handled | Yes — included in price | Often charged extra | Builder asks you to apply |
| Party wall surveyors | Instructed by us | Your responsibility | Skipped (illegal) |
| Building control | Plans + site inspections booked by us | Building Notice route | Not registered |
| Project management | Dedicated PM, weekly photo updates | Foreman doubles up | Owner-manager juggles 5 jobs |
| Payment schedule | Stage payments against signed-off milestones | Weekly invoices | Cash up front |
| Insurance | £10M PL + 10yr structural warranty | £2–5M PL only | No documented cover |
| Snags at handover | <3 typical | 20–30 typical | Walk-off mid-job common |
| Variation creep | 0% — fixed scope | +15–25% over original quote | +40%+ regularly |
Save £33,600–£75,600 on a house extension.
Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £168,000.