Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Kensington and Chelsea · SW7 · 2026

Stucco facade restoration + interior LBC works

Kensington and Chelsea · SW7 · Grade II listed · 38-week build

Project cost
£685,000
Site programme
38 wks
Type
Heritage Renovation + Listed Building Consent
Year
2026

Brief

A Grade II listed 6-storey Victorian stucco terrace in SW7 (close to the Royal Albert Hall) required full restoration after 40 years of unsympathetic refurbishments by previous owners. Scope: full external stucco repair and limewashing, restore all 24 original sashes with secondary glazing, internal reconfiguration of lower ground (kitchen and family room) and second floor (master suite), restore original plasterwork throughout, replace 1980s heating with new boiler and underfloor heating system, full rewire to heritage standards.

Challenge

Grade II listing meant every internal alteration required Listed Building Consent. The original 1860s plan form had been heavily modified — original servants' kitchen at lower ground had been replaced with a 1980s plywood kitchen and false ceiling concealing original cornice. The first-floor drawing room ceiling cornice had collapsed in two sections. Original plaster mouldings, marble fireplaces and timber panelling were partially intact but covered with 40 years of paint and modern intervention. The stucco facade was cracking in multiple locations from previous cement-based render repairs (incompatible with original lime substrate). RBKC heritage team required parallel LBC for: removal of all non-original partitions; reinstatement of historic plan form; restoration of damaged plasterwork to original profile; lime render and limewash facade restoration; sash window restoration (not replacement); secondary glazing to heritage spec.

Solution

Two-stage LBC application: Stage 1 covered external stucco restoration, sash windows and roof works (granted at 14 weeks). Stage 2 covered internal alterations, plan reconfiguration and plasterwork (granted at 18 weeks). Phased build over 38 weeks. External: stucco stripped to substrate, original lath repaired, lime render applied in three coats with hair binder, hand-finished and limewashed in a custom colour matched to original samples discovered behind shutters. Original ironwork balustrade lifted off, taken to specialist forge for stripping and re-galvanising. All 24 original sashes restored using the split-strip-restore method by Sash Window Workshop; secondary glazing magnetic units fitted internally. Internal: original plasterwork repaired by The Plasterwork Company using lime plaster and traditional fibrous methods; collapsed cornice replicated from in-situ samples. Marble fireplaces stripped of paint and re-polished. Lower ground floor: bespoke kitchen with heritage-style joinery, traditional tiled splashback, brass tapware. Second floor: master suite reconfiguration with restored panelling. Services: new system boiler concealed in basement plant room; underfloor heating on lower ground and second floor (over original timber joists with screed); heritage radiators on principal floors. Rewire to BS 7671 with concealed surface mount in oak skirting and lime plaster chase.

Outcome

Both LBC applications approved within target. Build delivered in 38 weeks against 38-week programme. RBKC conservation officer attended ten site visits during construction; the project was awarded a 2026 RBKC Heritage Award commendation. EPC improved from band F (35) to band D (66) — limited by listing constraints. Floor area unchanged. Independent valuation uplift £1,150,000 against £685,000 spend.

Spec

Project specification.

Listing
Grade II — both interior and exterior protected
LBC stages
2 (external + internal) both approved first-time
Stucco
100% stripped to substrate, re-rendered in three lime coats
Sashes restored
24 (full split-strip-restore + secondary glazing)
Plaster restoration
65m of cornice reinstated, 12 ceiling roses replicated
EPC
Band F (35) → Band D (66) — capped by listing
Programme
38 weeks site, 16 months total including LBC stages

Gallery

Inside the build.

Restored stucco facade
Front elevation: stucco repaired, lime-rendered and limewashed; ironwork restored
Drawing room with restored cornice
First-floor drawing room with restored original plasterwork and original sashes
Kitchen at lower ground floor
Bespoke kitchen at lower ground level with heritage tiles and brass tapware
Master suite second floor
Master suite at second floor with restored marble fireplace and panelled walls

"Builderr ran the LBC process in parallel with phased site delivery — a level of project orchestration we hadn't seen on previous heritage projects in the borough. The conservation officer commented at the final inspection that the limewashing and plaster restoration set a new benchmark for what's achievable on a Grade II terrace in this part of London."

Henry and Lavinia Marchbank, South Kensington SW7

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£685,000
a heritage renovation + listed building consent · no provisional sums
Typical builder + variations
£822,000
+£137,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£993,250
+£308,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £137,000£308,250 on a heritage renovation + listed building consent.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £685,000.

Want a build like Kensington and Chelsea?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.