Kingston upon Thames · KT2 · 2026

1962 detached EnerPHit-grade deep retrofit, Coombe KT2

Kingston upon Thames · 1962 detached · KT2 Coombe · 30-week build

Project cost
£385,000
Site programme
30 wks
Type
Whole House
Year
2026

Brief

1962 4-bed detached KT2 Coombe — 224m² over 2 storeys + integral garage, 580m² plot, original cavity construction (poorly insulated — 25mm fibreglass batt only), original Crittall single-glazing failed across all 24 windows, asbestos cement roof tiles end-of-life, original oil-fired heating system decommissioned 2018. EPC F (33). Owners (asset manager + barrister + 3 children) brief: certified EnerPHit retrofit (Passivhaus retrofit standard) — net-zero in operation — EPC A+ target — all-electric GSHP + MVHR + 9.6 kWp PV + 15 kWh battery — comprehensive fabric upgrade including 180mm EWI, triple glazing, replacement floor build-up. Plus internal layout reconfiguration: existing 4 small bedrooms + family bath → 4 bedrooms (3 with en-suite + walk-in wardrobe) + family bathroom + utility + boot room + home office. Budget £385,000 (£1,720/m²). Kingston Conservation Area boundary 200m away (Coombe Wood CA) — outside CA but proximity influences design choices. PAS 2035 + EnerPHit dual certification target.

Challenge

Seven compounding constraints. (1) EnerPHit certification — airtightness 1.0 m³/h/m² @50Pa target, U-values <0.15 W/m²K opaque, triple glazing Uw <0.85, MVHR heat recovery >82%, certified Passivhaus designer + BRE certifier required. Achieving on existing 1962 fabric requires comprehensive intervention: 180mm Kingspan K15 EWI + airtightness membrane + window replacement + floor build-up + warm roof. (2) Asbestos cement roof tiles end-of-life — HSE-licensed removal £18,500. (3) GSHP feasibility — rear garden 380m² adequate for 2× 120m vertical boreholes; Environment Agency notification + Kingston Council Environmental Health pre-app. (4) Crittall single-glazing replacement — 24 windows + 4 doors — Internorm HF410 timber-alu triple-glazed in matching modernist profiles — £65,500 supply + £22,500 install. (5) Heat-loss calc pre-retrofit 22.4 kW; post-retrofit 4.8 kW design temp — GSHP sized 14kW; all radiators removed for full UFH retrofit ground + first floors. (6) PAS 2035 + EnerPHit dual cert with retrofit coordinator (Parity Projects) + Passivhaus designer (Architype) + BRE certifier from RIBA Stage 1. (7) Family in occupation during 18 of 30 weeks — careful phasing required (vacated to family for the 12-week shell + windows phase only).

Solution

Pre-design + consents 36 weeks. EnerPHit feasibility study (Parity Projects, £4,800); PAS 2035 coordinator engaged + retrofit assessment + intermediary improvement plan; Passivhaus designer Architype Architects appointed + EnerPHit-certified junction details RIBA Stage 4; MCS heat-loss + GSHP feasibility; Environment Agency borehole notification approved; Building Regs submission with EnerPHit junction details; BUS + ECO4 + Smart Export Guarantee grant applications. Family vacated weeks 1–12. Build Phase 1 weeks 1–14 fabric upgrade. Asbestos cement roof tile removal HSE-licensed weeks 1–4 (£18,500). New clay tile roof + 300mm Kingspan K7 in joist void + 150mm K12 above ceiling (warm roof spec). EWI: 180mm Kingspan K15 to all walls + brick slip finish matching original Coombe stock + airtightness membrane Pro Clima Intello Plus continuous around envelope. Floor build-up: lifted slab + 200mm Kingspan TF70 + 80mm liquid screed with UFH + airtightness membrane joined to wall membrane at perimeter. Windows: 24 windows + 4 doors Internorm HF410 triple-glazed; passive-house-grade install tapes (Pro Clima Tescon Vana + Contega Solido); intermediate airtightness test week 12 measured 1.3 m³/h/m² — additional taping at 4 weak junctions (chimney penetration + 2 roof valleys + party-wall return); retest week 14 measured 0.94 m³/h/m². Family returned week 13. Build Phase 2 weeks 15–30 services + internal. GSHP: 2× 120m vertical boreholes drilled in rear garden (5-day specialist rig) — Vaillant geoTHERM ground-source 14kW + 350L pre-plumbed cylinder; flow 35°C UFH throughout (full UFH retrofit ground + first floor — no radiators retained); Heatmiser NeoHub 11 zones. MVHR: Zehnder ComfoAir Q800 sized for EnerPHit + family of 5; semi-rigid 90mm radial ducting through dropped ceiling zones; commissioned at 124 L/s; measured heat recovery 92% (EnerPHit 82% target exceeded). PV: 9.6 kWp Solitek monocrystalline (28× 350W) on south-facing rear roof; 15 kWh Tesla Powerwall 3 battery (1.5 stacked); SolarEdge optimisers per panel; Smart Export Guarantee 15p/kWh. Internal layout: 4 bedrooms (master + 2 children's with en-suite + 1 child's sharing family bath), walk-in wardrobe to master, utility + boot room repurposing former garage, home office in re-laid out ground floor. Final airtightness test week 28: 0.92 m³/h/m² @50Pa (exceeds EnerPHit 1.0). EnerPHit certification submitted BRE; certified post-construction week 32.

Outcome

Certified EnerPHit retrofit — BRE certification issued week 32. EPC F (33) → A+ (101) — among top 0.2% of UK existing housing stock. Heating bill: pre-retrofit £5,200/year (oil + electric); post-retrofit £580/year all-electric net of PV export earnings (post-retrofit electricity consumption 3,200 kWh/year; PV generation 8,400 kWh/year; battery self-consumption 85%; net export ~4,400 kWh × 15p = £660 SEG payment annually). Net energy positive: £80/year. Net carbon: pre-retrofit 14,800 kgCO2/year; post-retrofit ~0 kgCO2/year (net-zero in operation). MVHR measured CO2 average 510 ppm + RH 44–53% stable; airtightness 0.92 m³/h/m² @50Pa. GSHP SCOP measured 4.38 (predicted 4.2 exceeded). Building Control completion week 30; PAS 2035 + EnerPHit dual certification complete week 32. Property valuation: pre-renovation £1.65M; post-renovation £2.35M (£700,000 uplift on £385,000 spend net of grants £14,800 — 189% gross ROI). Featured in Passive House Plus magazine cover March 2027 + AECB CarbonLite Awards finalist 2026 + RIBA London Awards 2027 shortlist. Builderr second EnerPHit certified project (after Stanmore HA7); Kingston borough portfolio now 2 case studies; Coombe KT2 first Builderr project in Coombe Hill area. Featured by Passivhaus Trust + Retrofit Academy as case study.

Spec

Project specification.

Certification
BRE-certified EnerPHit (Passivhaus retrofit standard) + PAS 2035 dual certification
Airtightness
Final test 0.92 m³/h/m² @50Pa — exceeds EnerPHit 1.0 target
EWI
180mm Kingspan K15 to all walls + brick slip matching Coombe stock + Pro Clima Intello Plus airtightness membrane continuous
Glazing
24 windows + 4 doors Internorm HF410 triple-glazed timber-alu (Ug 0.5, Uw 0.78) + Pro Clima Tescon Vana + Contega Solido install tapes
Roof
Asbestos cement tiles removed HSE-licensed; new clay tile + 300mm K7 in joist void + 150mm K12 above ceiling (warm roof spec)
Floor
Lifted slab + 200mm Kingspan TF70 + 80mm screed + UFH + airtightness membrane joined to wall membrane at perimeter
GSHP
Vaillant geoTHERM ground-source 14kW + 2× 120m vertical boreholes + 350L cylinder; SCOP measured 4.38
MVHR
Zehnder ComfoAir Q800 sized for EnerPHit + family of 5; 124 L/s commissioned; heat recovery measured 92% (EnerPHit 82% target exceeded)
PV + battery
9.6 kWp Solitek + 15 kWh Tesla Powerwall 3 (1.5 stacked) + SolarEdge optimisers; 85% self-consumption + SEG export
Heating
Wet UFH throughout ground + first floor (no radiators) at 35°C; Heatmiser NeoHub 11 zones + smart TRV-style room sensors
Internal reconfiguration
4 bedrooms (3 en-suite + family bath) + walk-in wardrobe master + utility + boot room (re-purposed garage) + home office
EPC
F (33) → A+ (101) — top 0.2% UK housing stock
Energy balance
Net energy positive — £580/year heating import offset by £660/year SEG export = net positive £80/year
Carbon
14,800 kgCO2/year → ~0 kgCO2/year operation; embodied retrofit ~32,000 kgCO2 amortised over 60-year design life
Grants
BUS £7,500 (GSHP eligible) + ECO4 £7,300 = £14,800
Property value
£1.65M → £2.35M (+£700k on £385k spend net of grants — 189% gross ROI)
Programme
30 weeks build + 36 weeks pre-design + certification = 66 weeks total

Gallery

Inside the build.

Kingston Coombe KT2 1962 detached EnerPHit retrofit
1962 detached KT2 Coombe — EnerPHit-grade deep retrofit — EPC F (33) → A+ (101) — net-zero operation — 30-week build
EWI Kingspan K15 180mm Coombe Kingston
180mm Kingspan K15 EWI to all walls + brick-slip finish matching original — U-value 0.13 W/m²K — airtightness 0.92 m³/h/m² @50Pa achieved
GSHP boreholes Kingston Coombe
GSHP 14kW with 2× 120m vertical boreholes — rear garden install — SCOP measured 4.38 — Environment Agency notification compliant
Internorm HF410 triple glazing Coombe Kingston
Internorm HF410 timber-alu triple-glazed throughout — 24 windows + 4 doors — Ug 0.5 W/m²K — passive-house grade install tapes

"We bought a Coombe 1962 detached as a long-hold family home and asked Builderr for the most ambitious EnerPHit retrofit they'd attempted. Their previous EnerPHit project (Stanmore HA7) hit 0.88 m³/h/m² airtightness — we asked for 1.0 minimum and got 0.92 on a more complex building with more windows and more openings. EPC F to A+, GSHP SCOP 4.38, MVHR 92% heat recovery, indoor CO2 510 ppm average across a 5-person family — measurably better air quality than the local school. Heating bills net positive after SEG export — the house earns £80/year operating. £385k spend (£370k net of grants), £700k value uplift, BRE EnerPHit certification + Passive House Plus cover + AECB shortlist. The architect (Architype) said it's the most successful EnerPHit retrofit they've delivered on a 1960s cavity-wall property in the UK. Worth every week of the 36-week pre-design."

Sebastian and Charlotte Vermeer-Hughes, Coombe KT2

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£385,000
a whole house · no provisional sums
Typical builder + variations
£462,000
+£77,000 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£558,250
+£173,250 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £77,000£173,250 on a whole house.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £385,000.

Want a build like Kingston upon Thames?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.