Ground-floor structural opening + twin chimney-breast removal
Lambeth · 1891 Clapham Old Town terrace · 9-week build
Brief
1891 Victorian closet-wing terrace in Clapham Old Town CA (SW4), kitchen extension already completed 2019 but cellular ground-floor plan retained as a separate scope. Family wanted the ground floor opened up: 4.8m structural opening between the front reception and existing kitchen-diner (full back-of-front-room spine wall removal), plus both chimney breasts removed at ground-floor level only (upper stack retained on gallows brackets) to free the reception and dining alcoves. No external alteration — Clapham Old Town CA only catches externally-visible work so the whole job runs as internal-only permitted development under building control.
Challenge
1891 lime-mortar spine wall is 225mm solid London stock brick supporting the upper floors and the closet-wing back addition. Single 4.8m span required 305×165 UC44 (not standard 203 series) plus padstones into both party walls — significant propping at 600mm needling centres with timber sole plates and lime-mortar bedjoint preservation. Both chimney stacks (front reception + rear dining) needed ground-floor breast removal with gallows-bracket retention of the upper 3-storey stack — SE design required hanging-beam check for each. Two Party Wall awards (left + right) covered both the spine RSJ landing into party walls + the gallows brackets cantilevering off the party wall masonry. Family in residence throughout — work phased to keep one floor habitable each week.
Solution
Pre-build 7 weeks: structural engineer (Price & Myers) survey + calculation pack £1,650 fixed-fee week 1; Lambeth building control Full Plans submitted week 2, approved week 6 with no comments; 2 Party Wall awards via Berryman week 7. 9-week site: weeks 1–2 propping installation (needling at 600mm centres into both party walls with timber sole plates, acrows to floors above) + careful demolition of 4.8m spine wall section in brick courses retaining adjacent lime-plaster ceiling line; weeks 3–4 305×165 UC44 installed flush with existing ceiling, bearing onto Class B engineering-brick padstones bedded in 3:1 sand-cement on both party walls (Party Wall awards permitted padstone landing); weeks 5–6 twin chimney-breast removal at ground-floor level only — front and rear stacks — with bespoke gallows brackets (1m × 600mm steel triangulated, bolted into party-wall brickwork via M16 chemical anchors on Hilti HIT-HY 200 epoxy, designed by SE for 3-storey upper-stack dead load + wind); weeks 7–8 lime-plaster reinstatement to exposed brick reveals + Crittall W20 3-panel internal screen between snug and kitchen-diner (true Crittall, not aluminium W30) creating the broken-plan zone; week 9 making-good, F&B paint, redecoration of original cornice + ceiling rose (all retained). No external alteration so no planning required.
Outcome
Site completed week 9, on programme. 4.8m structural opening achieved with the RSJ tucked flush above the existing ceiling cornice line — no downstand, no visible beam, single continuous ceiling from front bay to rear closet wing. Both chimney breasts removed at ground floor with gallows brackets cantilevering off party walls — building control sign-off without remediation. Original ground-floor cornice, ceiling rose and dado rail all retained throughout. Crittall W20 3-panel internal screen marks the broken-plan zone (per Wandsworth / Lambeth current trend over fully open-plan) between snug and kitchen-diner without losing sightlines. Resale-equivalent uplift £128k on £38.5k spend = 233% gross ROI — top-decile for a structural-alterations-only scope. First Builderr ground-floor twin gallows-bracket retention (both stacks retained above) — used as portfolio reference for Lambeth + Wandsworth Victorian-terrace open-plan enquiries.
Spec
Project specification.
Gallery
Inside the build.
"We'd done the kitchen extension in 2019 but the ground floor was still cellular — separate front reception, then closed wall through to the kitchen-diner. We wanted it opened up properly, plus both chimney breasts pulled out at ground-floor level only (we wanted the upstairs fireplaces kept). Price & Myers designed the 4.8m spine RSJ and the gallows brackets for both stacks. Builderr did the heritage propping with needling at 600mm centres — really important on Victorian lime-mortar work, you can't just slap acrows on it. Berryman ran the Party Wall awards for the two neighbours covering both the RSJ landing into party walls and the gallows brackets cantilevering off the party-wall brickwork. The RSJ is tucked flush above the cornice line — no downstand, single ceiling from bay to closet wing. We added a Crittall W20 internal screen between the snug and the kitchen-diner so we still get the broken-plan zoning without losing sightlines. £38.5k all-in for the structural scope. Resale-equivalent uplift £128k = 233% ROI. Best money we've spent."
— Sarah & Michael R., Clapham Old Town SW4
Builderr vs other London builders.
The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.
| Criterion | Builderr | Typical London builder | Cowboy outfit |
|---|---|---|---|
| Labour model | Directly employed team (PAYE) | Mixed subcontract gangs | Day-rate cash labour |
| Pricing | Fixed-scope itemised quote | Estimate + provisional sums | Verbal price + variations |
| Design & engineering | In-house architect + SE | Outsourced, separate billing | Builder draws on the back of an envelope |
| Planning + LDC handled | Yes — included in price | Often charged extra | Builder asks you to apply |
| Party wall surveyors | Instructed by us | Your responsibility | Skipped (illegal) |
| Building control | Plans + site inspections booked by us | Building Notice route | Not registered |
| Project management | Dedicated PM, weekly photo updates | Foreman doubles up | Owner-manager juggles 5 jobs |
| Payment schedule | Stage payments against signed-off milestones | Weekly invoices | Cash up front |
| Insurance | £10M PL + 10yr structural warranty | £2–5M PL only | No documented cover |
| Snags at handover | <3 typical | 20–30 typical | Walk-off mid-job common |
| Variation creep | 0% — fixed scope | +15–25% over original quote | +40%+ regularly |
Save £7,700–£17,325 on a structural alterations.
Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £38,500.