Skip to content
ProjectsCost GuidesGuidesAnswersInsightsAbout
Get a Quote
Merton · SW19 · 2026

Hip-to-gable loft + ASHP & solar, Wimbledon

Merton · 1935 semi-detached · SW19 · 14-week build

Project cost
£117,000
Site programme
14 wks
Type
Loft Conversion
Year
2026

Brief

A 1935 semi-detached in Wimbledon Park — end of a quiet cul-de-sac, not in a conservation area and outside Wimbledon's Article 4 zone — offered ideal hip-to-gable geometry. The clients wanted a master suite at roof level plus a serious EPC uplift: the existing E-rated house was costing £3,200/year in gas. Brief: hip-to-gable loft with en-suite, ASHP replacing gas boiler, and south-facing PV solar.

Challenge

Hip-to-gable conversions on 1935 semis require the party wall between the two halves of the pair to be extended vertically to form the new gable — a structural operation that triggers a Party Wall Award on both the shared wall and the rear garden boundary if a neighbour's outbuilding sits within 3m. The adjoining owner had a brick outbuilding 1.8m from the shared boundary. Two separate Party Wall notices were required; the neighbour instructed their own Surveyor (Agreed Surveyor refused), adding 12 weeks to pre-construction. ASHP location was constrained: Merton's permitted development rules for heat pumps exclude the front of the property and the side elevation visible from the highway — rear garden only, with 1m setback from boundaries.

Solution

Party Wall Agreements: shared wall Award (new gable extension) and rear boundary Award (foundation vibration from scaffold) both sealed at week 9 of pre-construction. Hip-to-gable executed by building a new blockwork gable from first-floor plate height; the original hip rafters removed; new ridge extended; full-width rear dormer 5.8m wide × 2.4m high in smooth painted render (Merton DM Policy D2 — no clay tile requirement outside CA). Master suite 24m², walk-in wardrobe, en-suite with UFH. Velux rooflight to new gable face (north elevation — borrowed light). ASHP (Vaillant aroTHERM Plus 7kW, MCS accredited) positioned in rear garden 1.4m from boundary; 8 × 400W PV panels (3.2kWp) to south-facing rear roof slope via structural bracket into new dormer cheek rafters. BUS grant £7,500 applied; SEG export tariff registered with Octopus.

Outcome

Floor area added: 24m² master suite + 6m² walk-in wardrobe. EPC improved from E (47) to B (84) — the combined effect of ASHP, PV and enhanced roof insulation (PIR 150mm between/below rafters, U-value 0.13 W/m²K). Modelled gas bill eliminated; electricity bill net of SEG export estimated £640/year vs former £3,200/year gas. Party Wall process extended pre-construction to 14 weeks — Builderr absorbed this into programme without delaying the site start. Build completed 14 weeks; total project 28 weeks from instruction.

Spec

Project specification.

Loft type
Hip-to-gable with full-width rear dormer (5.8m)
Floor area added
24m² master suite + 6m² walk-in wardrobe
Gable
New blockwork gable from first-floor plate; ridge extended 2.1m
Party Wall
2 Awards (shared wall + rear boundary); 14-week pre-construction
ASHP
Vaillant aroTHERM Plus 7kW (MCS); BUS grant £7,500; rear garden 1.4m from boundary
Solar PV
8 × 400W panels (3.2kWp); SEG export via Octopus
EPC
E (47) → B (84)
Programme
14 weeks build, 28 weeks total (incl. 14-week Party Wall pre-construction)

Gallery

Inside the build.

Hip-to-gable loft conversion 1930s semi Wimbledon SW19
Hip-to-gable dormer extends full width of the 1935 semi — 24m² master suite at roof level
Master bedroom ensuite Wimbledon loft
En-suite with heated floor — short services stack directly above existing first-floor bathroom
Air source heat pump and solar panels Wimbledon
6kW ASHP replaces ageing gas boiler; 8 × 400W PV panels on south-facing rear slope

"The Party Wall process took longer than we expected but Builderr warned us and held the programme. The ASHP and solar have completely changed our energy costs — we haven't paid a gas bill since completion. The loft is the room everyone ends up in."

Tim and Claire Ashworth, Wimbledon SW19

Compare

Builderr vs other London builders.

The construction industry has a wide distribution of operators. Here's what changes between a directly-employed, fixed-scope outfit and the alternatives.

Builderr fixed price
£117,000
a loft conversion · no provisional sums
Typical builder + variations
£140,400
+£23,400 vs Builderr (≈20% overrun)
Cowboy outfit + cost creep
£169,650
+£52,650 vs Builderr (≈45% overrun)
CriterionBuilderrTypical London builderCowboy outfit
Labour modelDirectly employed team (PAYE)Mixed subcontract gangsDay-rate cash labour
PricingFixed-scope itemised quoteEstimate + provisional sumsVerbal price + variations
Design & engineeringIn-house architect + SEOutsourced, separate billingBuilder draws on the back of an envelope
Planning + LDC handledYes — included in priceOften charged extraBuilder asks you to apply
Party wall surveyorsInstructed by usYour responsibilitySkipped (illegal)
Building controlPlans + site inspections booked by usBuilding Notice routeNot registered
Project managementDedicated PM, weekly photo updatesForeman doubles upOwner-manager juggles 5 jobs
Payment scheduleStage payments against signed-off milestonesWeekly invoicesCash up front
Insurance£10M PL + 10yr structural warranty£2–5M PL onlyNo documented cover
Snags at handover<3 typical20–30 typicalWalk-off mid-job common
Variation creep0% — fixed scope+15–25% over original quote+40%+ regularly
Bottom line

Save £23,400£52,650 on a loft conversion.

Industry data (FMB, RICS, Which? Trusted Trader 2024) shows the average London construction project overruns by 18–22% on cost and 25–35% on time. Fixed-scope contracts with a single accountable team eliminate that variance. The savings above assume a typical project at £117,000.

Want a build like Merton?

Get a fixed-scope quote with the same direct-labour delivery. Senior consultant call within one business hour.

Related services